Skip Ribbon Commands
Skip to main content
 
 
Construction Project

Lakeshore Drive Realignment & Centennial Park Improvements

This project realigns Lakeshore Drive onto the former railroad bed & expands Centennial Park Waterfront parkland. The parkland expansion will be a combination of green recreational space, pathways & parking lots. The estimated project cost is $27M, including detail design, utility relocations & construction activities. See background and frequently asked questions.

Project Updates

September 21, 2016

Lakeshore Drive will be closed in both directions from Tiffin Street to Simcoe Street from Monday, Sept. 26 at 7 a.m. to Friday, Sept. 30 at 5 p.m. The detour route will be along Bradford Street, via Tiffin Street and Simcoe Street. The Tiffin Boat Launch will remain open during this time and pedestrians can cross Lakeshore Drive at Victoria Street to access the Marina and beach.

The full closure of Lakeshore Drive is required so the contractor can complete asphalt repairs under warranty from the recent re-construction. Signs advising of the road closure were posted last week.

Centennial Park Update

Starting this week, work will ramp up on the Centennial Park improvements. More fencing will be installed at the north end of the park on Thursday, Sept. 22 and in about 2 weeks fencing will be installed in the area of the playground. The fencing will largely prevent access to the open green space in the park, however, the following will remain open and accessible throughout construction:

  • Pedestrian and cycle trail
  • Public washrooms
  • Beach
  • Playground (except the swings, which will be removed in October)

Access to the pedestrian and cycle trails will be available at Victoria Street, the Marina boat launch and at the Dyments Creek Bridge. The Marina boat launch and North Centennial Parking Lot will be closed on Oct. 17 until Spring 2017.

January 4, 2016 

December saw the completion of the culvert extensions and the new channel being opened up at Bunkers Creek. A new section of cycling trail passes over the new culverts.

Paved entrances to the beach parking and the marina boat launch from the new Lakeshore Dr. are also now complete.

Watermains will be completed in early January allowing the remaining excavation for the Dyments Creek channel between the new Lakeshore Dr. and Kempenfelt Bay.

Dyments Creek flow should be making its way under the Lakeshore Dr. and through the new channel by the end of January.

Remaining landscape work as well as repairs to the Lakeshore Dr. top lift of asphalt will be carried out in the Spring of 2016. This will represent the completion of the current contract.

 

 
2015 Updates

October 5, 2015
The City of Barrie’s first Mayor, Willard Kinzie and Mayor Jeff Lehman helped to officially open the new Lakeshore Drive this afternoon. The two of them took a quick spin on the new road, driving a 1967 Monaco 500. The car was lent to the Mayor and former Mayor for the event by Barrie Thunder Classics, a local club dedicated to the preservation and enjoyment of classic and custom cars and trucks. Media Release

September 25, 2015
The new Lakeshore Drive will open to the public on October 5th at 5:00pm! The road has been realigned onto the former railroad bed, which allows for expanded waterfront parkland. The parkland expansion will increase the green recreational space available on the waterfront. Centennial Park improvements  are anticipated to commence in 2016.

August 27, 2015
Curb and gutter as well as the first lift of asphalt is in place from Toronto Street to just north of Dyment’s Creek. Heritage lighting is installed through the same section with tree planting underway north of Bunker’s Creek Bridge. The balance of the road work will be complete with traffic switching over to the new road in late September. Site preparation has started in Centennial Park for the construction of the new channel for Dyment’s Creek plus the construction of the new bridge abutments for the Dyment’s Creek pedestrian bridge through the park. Pedestrian traffic will be re-routed around the construction site for approximately 3 months.

June 30, 2015
Victoria Street has again been opened to through traffic between Lakeshore Drive and Ellen Street. Paving of Victoria Street between Bradford Street and Lakeshore Drive is expected to take place Monday, July 6th, weather permitting. There will be some temporary closures of Victoria Street to facilitate the paving operations during this time. The paving operations are expected to be completed the same day and the road will be opened upon completion. Access to properties from Ellen Street will not be affected. Access for emergency vehicles will be maintained.

June 2, 2015
The helical piles and grade beams to support the storm sewers are complete north of Victoria Street and will be complete in June for the balance of the site. Victoria Street is closed at Lakeshore until the end of June to allow for pile, grade beam and sewer installation. The temporary diversion of Lakeshore Drive through the marina parking lot will be left in place until the traffic is moved onto the new alignment which is expected in July. The road bed north of Victoria Street is complete up to Granular ‘B’ and ready for PowerStream electrical installations to be followed by curb, gutter and sidewalks.

April 2, 2015
Piles and grade beams to support the storm sewers will continue through spring. There will be a temporary diversion of Lakeshore Drive this spring through the Marina Parking Lot.  This will allow for the underground piping and curb work across the existing section of Lakeshore at the north end of the project. Preparation of the new Lakeshore Drive road bed will start this month.

February 27, 2015
Winter work continues with dewatering and helical pile foundations, grade bream, storm sewers, oil/grit separators and sanitary sewers, all on Lakeshore Drive.  The existing Lakeshore Drive and Victoria Street are both fully open to traffic.

January 19, 2015
Contractor is continuing with work throughout the winter as weather permits.  Work currently underway includes the helical pile foundations, grade beam and storm sewer on Lakeshore Drive, North of Victoria Street. Excavation for storm sewer foundations South of Victoria Street is expected to commence later this month. Lakeshore Drive and Victoria Street are both fully open to traffic and disruptions are anticipated to be minimal in the foreseeable future.

2014 Updates

November 20, 2014
Helical pile foundation installation has been completed on Victoria Street and is currently underway on Lakeshore Drive for the storm sewer works adjacent to Bunker’s Creek. Completion of restoration on Victoria Street and its subsequent reopening is anticipated by Thursday, November 27, 2014.

August 29, 2014
Dewatering installation has been partially completed and will resume once helical pile installation begins. Helical pile testing is underway prior to the installation of production piles. Road Closure Notice: Victoria Street will be closed from Bradford Street to Lakeshore Drive for pavement rehabilitation and installation of underground infrastructure. Road closure will be in effect from September 3, 2014 and should be reopened by September 24, 2014.

July 30, 2014
The City of Barrie has awarded the Phase 2 Lakeshore construction project to Harvie Construction Inc. This phase involves the reconstruction of Lakeshore Drive from Toronto Street to Tiffin Street on a new alignment west of the existing roadway.

  • Traffic Impacts

    During Kempenfest 2014, parking on the gravel areas west of Lakeshore Drive will be available. However, after Kempenfest the existing gravel parking area between Victoria Street and Toronto Street will be closed to public access and will not be re-opened, as the contractor will commence installations in preparation for dewatering relating to storm sewer works.

    The existing gravel parking areas between Victoria Street and Tiffin Street will remain open to public parking until approximately mid-August, at which time preparation for dewatering will commence.

    Pedestrian movements along the waterfront paths will remain unobstructed. General information: Traffic & Park Events During Construction

July 11, 2014
Bunker’s Creek and Dyment’s Creek bridge structures are complete. Outstanding works include the decorative stone facing, parapet railings and site cleanup. Award of Contract 2 for the realignment of Lakeshore Drive is imminent, with grading works commencing shortly thereafter.

March 27, 2014
Bunker’s Creek bridge substructure is complete with the exception of the erosion control slab underneath the bridge. Superstructure work continues with the placement of the hollow core slab girders (photo) on the abutments. Upcoming work will include forming, steel and concrete placement for the deck, approach slabs and barrier walls. Dyment’s Creek bridge precast spans have been placed, with preparatory work for the deck, wingwalls, erosion control slab and barrier walls ongoing.

January 31, 2014
All pile driving on this project is complete. Dewatering is in full operation to ensure buried structure components are constructed in dry conditions and will be deactivated at each site when all creek-level works are completed. Bunker’s Creek bridge substructure construction continues, including formwork, steel and concrete placement for the wingwalls and the erosion control slab. Dyment’s Creek bridge work continues with excavation and preparatory work for footing construction.

2013 Updates

December 20, 2013
Final testing on the piles driven at Dyment’s Creek is still in progress; completion is scheduled for early January, 2014.

Bunker’s Creek bridge substructure construction continues, including formwork, steel and concrete placement for the abutments, wingwalls and the erosion control slab. Dewatering is in full operation to ensure buried structure components are constructed in dry conditions.

The Contractor has scheduled a holiday shutdown between December 23, 2013 and January 3, 2014. Work is expected to restart as early as January 6, 2014.

December 6, 2013
Production pile driving is complete at the Dyment’s Creek bridge site. Final testing will be carried out in the coming week which will include periodic re-tapping of piles.

Footing construction, including formwork, steel & concrete placement is ongoing at the Bunker’s Creek bridge site. Dewatering is in full operation to ensure the footing is constructed in dry conditions.

November 22, 2013
Pile driving operation was previously completed at Bunker’s Creek bridge site and Contractor commenced excavation & construction of bridge footings. Pile driving continues at the Dyment’s Creek bridge site and completion is anticipated in the first week of December.

October 7, 2013
Pile driving operation is in progress at the Bunker's Creek bridge site and is expected to last until approximately the third week of October before moving to the Dyment's Creek site.

September 23, 2013
Dyment's Creek diversion is complete.

September 14, 2013
Turtle hatchlings released at Bear Creek Ecopark. more info

August 26, 2013
Pile driving has commenced.

August 19, 2013
Bunker's Creek diversion is complete.

July 29, 2013
General Contractor has mobilized to site.

July 9, 2013
Turtle nest removed and sent for off-site incubation. more info

Project Features

Roadway Improvements:

  • Reconstructing Lakeshore Drive from Toronto Street southerly to approximately 100 m north of Tiffin Street (i.e. at Hotchkiss Creek) with storm sewer, curb and gutter, a raised centre median, and on-street parallel parking;
  • Continuous sidewalk on the west side from Toronto Street to Tiffin Street;
  • Continuous bicycle path on the east side of Lakeshore Drive (in Centennial Park);
  • New traffic signals at the Victoria Street-Lakeshore Drive Intersection with audible and visible pedestrian crossing signals;
  • New traffic signals between Dyment's Creek and Hotchkiss Creek at the parking lot access on Lakeshore Drive with audible and visible pedestrian crossing signals;
  • Reconstruct Victoria Street from Ellen Street to Lakeshore Drive;
  • Resurface Victoria Street from Bradford Street to Lakeshore Drive;
  • Improved street lighting on Lakeshore Drive and Victoria Street;
  • Enhanced landscaping for the raised median and west boulevard treatment.

Bunker's Creek Improvements:

  • A single span bridge with an opening that has a 14m span and a 1.5m high opening for creek flow;
  • Grading across the roadway for major storm event flows;
  • Creek daylighting with fish habitat enhancements between the Marina bicycle path and the new Lakeshore Drive roadway (i.e. where the Lakeshore Drive roadway is today); and,
  • Extending the box culvert system under the Marina Boardwalk upstream to be under the bike path, too;

Dyment's Creek Improvements

  • A single span bridge with an opening that has a 12m span and a 1.8m high opening for creek flow;
  • Grading across the roadway for major storm event flows;
  • Creek daylighting with fish habitat enhancements between Kempenfelt Bay the new Lakeshore Drive roadway (i.e. through Centennial Park);
  • Dredging the silt from the pond between Bradford Street and Lakeshore Drive to create a low flow channel and a storm overflow ponding area;
  • A pedestrian path extending from Lakeshore Drive to the dead end bulb of Ellen Street.

Centennial Park Improvements
Subject to approval by Council

  • Realigning the pathway and improving the lighting and bench locations from the Marina southerly to Hotchkiss Creek;
  • Adding a new pedestrian bridge across the Dyment’s Creek channel that will extend through the park;
  • Creating event areas and general recreation areas;
  • Enlarging the parking lots in Centennial Park to increase parking from a total of approximately 210 stalls to 450 stalls;
  • Enhancing the landscaping to restore the areas disturbed by the construction activity, while protecting and preserving the landscaping that should not have to be disturbed by construction.

Schedule

Council, as part of approving the 2013 Capital Budget, adopted a construction schedule for this project that is 4 years, based on the following order of events:

2013
  • Construction of the Bunker's Creek Bridge and the Dyment's Creek Bridge on the proposed Lakeshore Drive alignment.
2014
  • Completion of the Bunker's Creek Bridge and the Dyment's Creek Bridge
  • Construction of the new Lakeshore Drive (except for the street  lighting and top lift of roadway asphalt)
  • Reconstruction of Victoria Street
2015
  • Addition of street lighting on Lakeshore Drive
  • Placement of the top lift of asphalt on Lakeshore Drive and Victoria Street
  • Transfer of traffic onto the new Lakeshore Drive roadway
  • Creation of the open channel through Centennial Park for Dyment's Creek
  • Creation of the open channel for Bunker's Creek between the Marina and the new Lakeshore Drive
2016–2017
  • Centennial Park Improvements 
    Subject to spending approval by Council

Background: Lakeshore Drive Realignment & Centennial Park Improvements

Lakeshore Drive

In 2004, recommendations from an Environmental Assessment (EA) Study for Improved Accessibility to Barrie Downtown and Waterfront included recommendations for the Lakeshore Drive corridor. The EA Study began in 1999 and concluded in November 2004 with recommendations adopted by Council.

A number of construction projects have already implemented recommendations from the EA Study, including:

  • Work on Simcoe Street, from Bradford Street to Mulcaster Street (3 construction phases);
  • Work on Toronto Street from Lakeshore Drive to Ross Street (2 construction phases);
  • Work at the Tiffin Street-Lakeshore Drive-Bradford Street-Essa Road Intersections

Bunker’s Creek and Dyment’s Creek

In 2001, Council adopted the recommendations in an EA Study for the Bunker’s Creek Master Drainage Plan. In general, the recommendations focus on improved creek flow capacity, creek channel stabilization and enhanced fish habitat.

Bunker’s Creek from Bradford Street downstream across Lakeshore Drive to Kempenfelt Bay (at the Marina) the recommendations provide road crossing culvert sizing and channel improvements.

In 2006, Council adopted the recommendations in an EA Study for the Dyment’s Creek Master Drainage Plan. In general, the recommendations focus on improved creek flow capacity, creek channel stabilization and enhanced fish habitat.

Dyment’s Creek from Bradford Street downstream across Lakeshore Drive to Kempenfelt Bay (at the Rotary Fountain at the south end of Centennial Beach) the recommendations provide road crossing culvert sizing and channel improvements through Centennial Park, and improvements to the pond between Bradford Street and Lakeshore Drive.

Frequently Asked Questions
Is the new roadway able to accommodate emergency vehicles?

Barrie Fire and Emergency Service reviewed and signed off on the design and, since the implementation of the new Lakeshore Drive in October 2015, BFES has confirmed that there are no concerns regarding response time to emergencies that may occur along any section of the lakeshore.

The Lakeshore Drive design follows the recommendations from the Waterfront/Downtown Transportation Improvements Class Environmental Assessment, completed in November 2004. The recommendations acknowledge a fine balance between the needs for:

  • vehicles accessing the waterfront and downtown;
  • pedestrians accessing the waterfront and downtown;
  • cyclists and rollerbladers accessing the waterfront and downtown;
  • boaters accessing the waterfront;
  • vehicles parking in parking lots along the waterfront;
  • vehicles parking on the street

Through the design process, City staff implemented industry standards and safety requirements including City of Barrie standards, Transportation Association of Canada design standards, Ontario Ministry of Transportation Geometric Design Standards, and Ontario Provincial Standards for Roads and Public Works.

There was a conscious desired effect of narrower roads to provide traffic calming that benefits pedestrians, cyclists, and other parks users. There are minimal access locations required as there is limited access points to other public or private property on the west side of the new Lakeshore Drive.

How will access to parking be affected once this project is complete?

While some former gravel area along Lakeshore will be converted into green space/pathways, the amount of formal parking spots will double.

The Marina Parking Lot currently has 34 spaces for vehicles and 11 spaces for vehicles with trailers; this lot have only one access. The other parking lots between Hotchkiss Creek and Toronto Street, with the majority of the lakefront parking capacity, will have 2 accesses. In addition, the one large parking lot south of Centennial Park will have traffic signals for one access.

How were traffic & park events impacted during the roadway construction?

In general, the new roadway construction was not on the existing roadway that occupied vehicular traffic. The contractor was required to provide at least 1 lane for vehicular traffic in each direction through the construction site when construction activity is encroaching the traffic lanes.

The contractor did close Lakeshore Drive for relatively short periods of time while the new roadway was tied into the existing roadway at Toronto Street and at Hotchkiss Creek Culvert Structure (near Tiffin Street).

The contractor had periodic delays to traffic while the construction equipment was performing some deliveries and turning maneuvers.

Emergency services received communications when the short term road closures were scheduled and when the roads were re-opened to through traffic. Detour routes during the road closures and sidewalk closures were signed within Barrie for the general public.

Pedestrian movement through the park were available during the various stages of construction.










Looks like your screen is a bit too small

The page you are attempting to view is not currently compatible with the dimensions of your device. Please visit this page on a larger screen.