Skip Ribbon Commands
Skip to main content
The Road Ahead

The Engineering department is responsible for project management, environmental assessment studies, design, contract administration, site inspection, field coordination services and surveys on municipal infrastructure projects.

Road Design Projects Underway
Related webpage: Completed Environmental Assessments
City
Budget
Expected
Construction Start
Harvie Road / Big Bay Point Road / Crossing of Highway 400
Connecting Harvie Road to Big Bay Point Road across Highway 400.
$2.6M 2019–20
Mapleview Drive Sanitary Forcemain Twinning & Pumping Station Upgrades
Upgrades to Holly Pumping Station & twinning of the sanitary forcemain on Mapleview.
$17M  2017–19
2017 Road Construction Projects
The below list is updated each spring
City
Budget
Expected
Completion
Asphalt Resurfacing
Various locations
$4.55M Sept. 2017
Centennial Park Improvements
Ongoing project (initiated in 2013)
$7.4M Nov. 2017
Cundles Road & Duckworth Street Reconstruction
Ongoing project (initiated October 2013)
$44.5M June 2017
Dunlop / Miller Intersection 
Dunlop St W & Tiffin St / Miller Dr intersection
$1.53M August 2018 
Essa Road ACDC New Railway Crossing 
Installation of grade crossing warning system (flashing lights, bells, gates & cantilever); modifications to traffic signals at Essa/Gowan & Tiffin/Essa/Bradford intersections.
$710K  Dec. 2017
Essa Road Infrastructure Improvements
Essa Rd, Anne–Gowan & Innisfil St, Essa–Caroline
$8.85M  Dec. 2017
Ferndale Drive North Reconstruction
Tiffin Street to Dunlop Street
$9.1M June 2017
Frozen Water Services
Work on existing water services at locations that have experienced freezing during extreme cold conditions. Residents will be given notification prior to any work on their water service.
 $1.18M  Sept. 2017
Glenecho & College Crescent Watermain 
Watermain replacement including road reconstruction.
 $900K  Dec. 2017
Johnson Street Improvements
Shanty Bay Rd to Lake Simcoe
$1.66M Dec. 2017
Little Avenue Retaining Wall 
Removal of segmental block retaining wall in front of 167 Little Ave; removal and partial replacement of segmental block retaining wall in front of 175 and 177 Little Ave. Retaining wall is complete. Restoration works including sidewalk, final grading, driveways and sod is on-going.
$180K Sept. 2017
Mapleview Drive East Improvements
Huronia Road to Country Lane
$13.3M Dec. 2017
McKay Road Bridge Replacement
At Highway 400 (Ministry of Transportation Project)
$2.5M Dec. 2017
Meridian Place Development  $5.2M Nov. 2017
Morrow Road Reconstruction
Ardagh Road to Patterson Road
$3.88M Fall 2018
Mulcaster Street Storm Outlet Replacement
Heritage Park
$1.13M July 2017
Rodney Street
Collingwood to Kempenfelt: Road reconstruction including replacement of existing watermain, sanitary sewer & storm sewer & installation of new concrete sidewalk.
 $900K Nov. 2017
Royal Oak / Gables (Phase Two) $11.94M* Nov. 2018
Sanitary Sewer Rehab (lining) 
Approximately 400m of cured In Place Pipe Sewer Rehabilitation for sanitary sewers on St. Vincent Street, Blake–Duckworth.
$315K
Oct. 2017
Sidewalk Infill (Ferndale & Wellington)
Maple Avenue Sidewalk 

Installation of concrete sidewalk on Wellington St. and Ferndale Rd. Replacement of existing sidewalk on Maple Ave. north of Dunlop St.
$1M  Fall 2017
Tiffin Street / Highway 400 Underpass Expansion
(Ministry of Transportation Project) 
$4.2M 2019
Trunk Watermains, Annexation Lands
Trunk watermains on Ashford Drive, Madelaine Drive, Sandringham Drive, Consort Drive, Sun King Crescent and Royal Jubilee Drive.
 $8.5M  2017–18

Watermain Cathodic Protection Program
Cathodic protection of approximately 7000m of watermain including installation of approx. 750 anodes & 60 tests stations. Various locations: Anne St, Autumn Rd, Coxmill Rd, Dunlop St, Essa Rd, Elliot Ave, Ferndale Industrial Dr, Garden Dr, Greenfield Ave, Hamilton Rd, Huriona Rd, Sarjeant Dr, Trillium Cres, Truman Rd, Welham Rd. Work is nearing completion and should be completed by mid-October.

 $865K  Sept. 2017
Watermain Replacement: Baldwin Lane & Grove Street
Baldwin Ln, Marshall–Bayview & Grove St, Davies–Cook: Road restoration, replacement of existing water services on both Baldwin & Grove, & replacement of sanitary sewer on Baldwin.
$1.84M Oct. 2017
(Top course asphalt June 2018) 
Interim Watermain Replacement
Replacement of galvanized steel watermains on Alfred St, Cumberland St, Florence St., Henry St, Jacobs St, John Terrace, Marcus St and Victoria St. Interim measure to improve watermain reliability until street is scheduled to be reconstructed, when watermain will also be upgraded to current standards.
 $230K June 2018
Wildflower Court Storm Sewer 
Installation of storm sewer including maintenance holes & catch basins, including restoration.
$275K Dec. 2017
*all phases


Looks like your screen is a bit too small

The page you are attempting to view is not currently compatible with the dimensions of your device. Please visit this page on a larger screen.