Anne & Innisfil Railway Crossing Upgrades - BCRY

This project is being undertaken to increase safety at the existing BCRY railway crossings on Anne Street and on Innisfil Street.

A consultant was retained in 2016 to complete an assessment of these railway crossings. Recommendations included gates be installed based on guidelines and best practices for safety.

Project Features

  • Installation of automatic grade crossing warning system, including gates, consisting of flashing lights.
  • Sidewalk Improvements.
  • Interconnection of the grade crossing warning system with the traffic signals.

Schedule

Estimated Start May 2018
Estimated Completion July 2018

Affected Services

Sanitary sewer, hydro, gas, telephone and cable TV services should not be affected by the construction, barring any unforeseen circumstances.

Water service may be interrupted for just a short duration in order to switch the water service over from the old watermain system to the new watermain system.

Curbside collection will not be affected. On your normal curbside collection day, area residents are asked to place all garbage, organics, recyclables and yard waste materials at the front of the property as usual. The construction contractor will remove these items and take them to outside of the construction zone for pickup by the City’s waste contractor. Garbage cans, organic bins and recycling boxes will be returned to the property later that day. Please mark your address on all of your containers.

Access to Properties

Access for emergency service vehicles will be maintained at all times.

Vehicle access to properties within the construction limits will be provided at almost all times throughout the construction period, however on various occasions direct access to driveways may be restricted.  Access to driveways will be restored as quickly as possible after the work causing the restriction is completed.

Pedestrian access to properties will be maintained throughout the duration of the construction.