2020 Asphalt Crack Sealing
This project is an annual program to seal cracks in asphalt pavement at various locations in Barrie. The routing and sealing operation will help to prevent cracking and slow pavement deterioration in the future.
The crack sealing program is part of the City’s annual pavement rehabilitation work and is a proven method in extending the service life of asphalt pavement.
Impacted Roadways
The crack sealing operation will be completed on various residential and arterial roads in the City. This year’s work is primarily focused in wards 3, 6, 7, and 9. See map to view specific road segments.
Schedule
Estimated Start: October 2020
Estimated Completion: November 2020
Affected Service
No service interruptions are anticipated.
Safety
The contractor’s work will be focused within the travelled roadway. Although the contractor is required to conduct their work in a safe manner, we ask that motorists take extra caution during the construction period.
Traffic & Access Impacts
Minor traffic impacts should be expected as a result of short-term lane closures for traffic control. Traffic flow will be maintained throughout the work and vehicles will be unimpeded from accessing residences.