Skip Ribbon Commands
Skip to main content
Sign In

Skip Navigation LinksAsphalt-Resurfacing 2018 Asphalt Resurfacing

Road Construction Project

2018 Asphalt Resurfacing

Project construction budget is $3.15M and expected completion date is Fall 2018. Asphalt resurfacing including concrete curb and sidewalk repairs on selected streets.

The asphalt surface of the noted streets has deteriorated with patches, multiple cracks and some rutting. The primary purpose of the asphalt road resurfacing is to prevent roads from deteriorating to the point that they would require more extensive and costly rehabilitation and/or reconstruction.

Completed roads are highlighted.

2018 Contract 1• Anne St. (Sunnidale to Neelands) 
• Cox Mill Rd. (Yonge to Dock Rd.) 
• Hanmer St. West (Anne St. North to Finlay) -
• Ferndale Dr. North (Benson Drive to Edgehill)               
2018 Contract 2• Lockhart Rd. (Finsbury St. to Yonge St.)                
• Huronia Rd. (Little Ave. to Yonge St.) 
• Ardagh Rd. (Ferndale Rd S.  to Wright Dr.) 
• Saunders Rd. (Lockhart to 600m North)  ​ ​
Micro-Surfacing​•  Ashdale Ct.
•  Baltimore Rd.
•  Benson Dr. 
•  Bluejay Dr.
•  Cardinal St.
•  Deerpark Dr.
•  Hodgson Dr.
•  Parkway Pl. ​
•  Rolston Dr.
•  Rosedale Pl.
•  Springdale Dr.
•  Woodgrove Ct​.
Reclamite Treatment​• Black Ash Tr.
• Cardinal St.
• Cedar Cres.
• Cherry Ct.
• Crew Ct.
Hickory Ln.
• Humber St.
Little Ave.
Lamont Cres.
Livingstone St. E.
McIntyre Dr.
Penvill Tr.
​• Pine Dr.
• Poplar Dr.
• Primrose Cres.
Purbrook Ct.
​• Silver Tr.
Spruce Cres.
St. Vincent St.
• Sunnidale Rd.
• Trotter Ct.
Walnut Cres.
• Wildflower Crt.

Project Updates

October 1, 2018

Micro-surfacing Contract – All streets are now completed with the exception of Aspen Drive, Chestnut Court and Hazel Avenue which will not have micro-surfacing completed on them.

Aspen Drive, Chestnut Court and Hazel Avenue had reclamite treatment applied to them this summer, so we will not complete any micro-surfacing on these streets. We apologize for the inconvenience or confusion this may have caused.   

September 26, 2018

Contract 1: All streets are now completed. Driveway restorations on Anne Street are still outstanding and shall be completed shortly.

Micro-surfacing: Completed roads are now highlighted above.The remaining roads will be completed by September 28.

September 21, 2018

The City’s early life pavement preservation program aims to preserve the asphalt surface of roadways while extending their service life. Beginning Sept. 24 the City is conducting pilot projects with two preservation techniques: micro-surfacing and Reclamite. As a result of this project, we anticipate a reduction in roadway maintenance costs and expensive roadway resurfacing construction. This allows us to allocate funding to other needs throughout the City while minimizing disruption to residents and providing better roads. 

Micro-Surfacing

Benson Dr. and Hodgson Dr. will be completed on Monday, Sept. 24 and Tuesday, Sept. 25. The remaining streets listed above will be completed from Wednesday, Sept. 26 to Friday, Sept. 28. Residents are asked to please refrain from parking on affected streets.
Reclamite TreatmentResidents are encouraged to avoid parking on affected streets listed above from Monday, Sept. 24, to Friday, Sept. 28 (between 7:30 a.m. and 6:30 p.m.).
Affected residents have received notification of this project in the mail.
September 11, 2018

Contract 1: Asphalt removal on Anne Street is scheduled to start Wednesday, September 12. All works on Anne Street is expected to be completed by September 28, 2018, weather-dependent.

August 24, 2018

Contract 1: Concrete work on Anne Street is on-going. Asphalt removal is scheduled for the beginning of September. Asphalt placement should be completed within two (2) weeks of asphalt removal, weather dependent.

Contract 2: All roads are completed. The Contractor is finishing some driveways and other deficiencies that are outstanding.

August 3, 2018

Contract 1: Coxmill Road has been completed. Concrete works on Hanmer Street have been completed. Asphalt removal on Hanmer is scheduled for Tuesday, August 7. Asphalt paving on Hanmer is schedule for Monday, August 13, weather dependent. Concrete work on Anne Street is ongoing.

Contract 2: Ardagh road has been completed. Asphalt paving on Saunders Road is completed. Site restoration including shouldering, line painting and driveways will be completed next week.

July 13, 2018

Contract 1: Concrete work on Hanmer Street is on-going.  Asphalt removal and placement is scheduled to begin on Coxmill the week of July 16, 2018.

Contract 2: Asphalt removal on Ardagh Road is completed. Base asphalt placement is scheduled to begin Friday, July 13. Top course asphalt will be completed the week of July 16, 2018 weather dependent. Work on Saunders Road is scheduled to begin the week of July 23, 2018.

July 3, 2018
Contract 1

Concrete removal and replacement on Gordon Court and Hanmer Street will begin the week of July 3, 2018.  Concrete work on Gordon Court is scheduled to be completed by July 6, 2018. Concrete work on Hanmer Street is scheduled to be completed in three (3) to four (4) weeks, weather dependent. Concrete work on Anne Street is scheduled to begin the week of July 23, 2018 and is expected to be completed within two (2) weeks weather dependent.  Asphalt work is scheduled for the end of July/ beginning of August, weather dependent.

Concrete work on Coxmill Road. Asphalt work from Hurst to Dock Road has been completed. Asphalt removal and placement from Hurst to Yonge is scheduled for the week of July 23, 2018, weather dependent.

Ferndale Road is completed.

Contract 2

Lockhart Road and Huronia Road are completed.

Concrete removal and replacement has started on Ardagh Road and is scheduled to be completed by July 6, 2018, weather dependent. Asphalt removal and replacement is scheduled for the week of July 9, 2018, weather dependent.

June 8, 2018
Contract 1Concrete work on Cox Mill is almost completed. Concrete work on Cox Mill will be completed by June 15, 2018. Concrete on Anne Street is scheduled to begin June 18, 2018.
Contract 2Asphalt paving on Lockhart was completed Friday, June 8.  Driveway restoration, traffic signal loops and shoulders on Lockhart will be completed by June 15, 2018.

Asphalt removal and paving is scheduled to begin on Huronia Road, Monday, June 18, 2018. Huronia Road will be closed daily from 7am to 7pm during the construction activities. The road will be opened nightly. The work on Huronia Road is scheduled to be completed by Friday, June 22, 2018.
June 1, 2018

Contract 2: The Contractor will begin asphalt removal on Lockhart Road on Tuesday, June 5, 2018. Lockhart Road (Finsbury to Yonge)  will be closed daily from 7am to 7pm for construction activities June 5 – June 13, when the work is expected to be completed (weather-dependent). The road will be opened for traffic each night. 

May 25, 2018

Contract 1: Asphalt grinding on Ferndale has been completed; top course asphalt on Ferndale is scheduled to be completed by Wednesday, May 30, 2018, weather dependent. Concrete work has begun on Cox Mill and will continue for the next two weeks. Asphalt removal on Cox Mill will begin after the concrete work has been completed.

May 11, 2018

Contract 1: Concrete removal and replacement has begun on Ferndale between Edgehill and Benson. Asphalt removal is scheduled to begin Tuesday, May 21 on Ferndale. Concrete work will begin on Cox Mill next week.

Project Features

Contracts 1 & 2:

  • Removal and replacement of some of the existing concrete curbs where necessary
  • Removal and replacement of some of the existing concrete sidewalk where necessary
  • Adjustment of existing frames and grates on catch basins including some replacements
  • Adjustment of existing frames and grates on maintenance holes including some replacements
  • Adjustment of existing water value boxes to grade including some replacements
    • Removal of existing asphalt (partial and some full depth)
    • Supply and placement of hot mix asphalt
    • Reinstatement of any traffic signal loops
    • Reinstatement of any pavement markings
    • Boulevard restoration (topsoil and seed/sod)
    • Driveway restoration

Micro-surfacing & Reclamite

The City’s early life pavement preservation program aims to preserve the asphalt surface of roadways while extending their service life. During the week of Sept. 24 2018 the City conducted projects with two preservation techniques: micro-surfacing and Reclamite. As a result of this project, we anticipate a reduction in roadway maintenance costs and expensive roadway resurfacing construction. This allows us to allocate funding to other needs throughout the City while minimizing disruption to residents and providing better roads. 

Schedule

Estimated construction start:June 2018
Estimated completion:Fall 2018

Affected Services

Water, sanitary, sewer, Hydro, Telephone, Cable TV, and gas services should not be affected by the construction, barring any unforeseen circumstances.

Curbside Collection: On the normal curbside collection day, residents are asked to place all garbage, organics, recyclables and yard waste materials at the front of your property as usual. The construction contractor will remove these items and take them to outside of the construction zone, for pickup by the City’s waste pickup contractor. Your garbage cans, recyclable items to the front of your property by 7 a.m. otherwise these items might not be picked up.

Access to Properties

All reasonable efforts will be made to maintain vehicle access to driveways. However, there may be some temporary interruptions to access during construction. Access will be restored as quickly as possible. The Contractor will provide prior notice of any imminent access restrictions to the businesses and residents. Pedestrian access to all homes and businesses will be maintained during construction.

Safety

The Contractor is required to conduct his work in a safe manner, including fencing of deep excavations, etc. We ask that you take extra caution during the construction period to ensure everyone’s safety.

Traffic Impacts

All road will remain open to through traffic during construction, although lane closures and restrictions can be expected in order to accommodate construction activities. We ask for your patience in such instances.

Looks like your screen is a bit too small

The page you are attempting to view is not currently compatible with the dimensions of your device. Please visit this page on a larger screen.