September 11, 2020Asphalt removal is anticipated to begin on Dunlop Street on the night of Monday September 14. Paving and line painting are anticipated to be completed by Friday, September 18, weather permitting. August 28, 2020
Asphalt removal and replacement on Dunlop Street is now anticipated to begin the week of September 16, weather permitting. August 21, 2020
Work on Saunders Road is generally complete.
Asphalt work on Dunlop Street is anticipated to begin the week of August 31, weather permitting.
Contrctor is currently working on any deficiencies or outstanding work on the completed streets.
August 14, 2020Work on Fraser Court is complete. Work on Saunders Road is nearing completion. Surface asphalt will be placed on Monday, August 17. The work on Dunlop Street is anticipated to begin the week of August 24, weather permitting. This work will occur at night.
August 7, 2020Work on Harding Avenue is generally complete. Line painting is scheduled to be completed early next week. Work on Fraser Court is nearing completion. Top asphalt placement is scheduled for Monday, August 10, weather permitting. Asphalt removal will begin on Saunders Road Monday, August 10. It is anticipated that the base asphalt will be placed Friday, August 14 and surface asphalt will be placed Monday, August 17, weather permitting. There will be a local road closure for this work. The road will be closed from 7am to 7pm during this work; it will be opened at the end of each day. Please do not park on the street during the hours of 7am to 7pm. Access will be maintained for emergency services and businesses. We ask that you try to limit driving in/out the construction area as much as possible during the work. It is anticipated the work will be complete by Monday, August 17 weather-permitting. July 31, 2020Work on Firman Drive and Herrell Avenue is generally complete. Work on Harding Ave is nearing completion and is anticipated to be complete by August 7, weather-permitting. Work will be begin on Fraser Court Tuesday, August 4. There will be a local road closure for this work. The road will be closed from 7am to 7pm during this work; it will be opened at the end of each day. Please do not park on the street during the hours of 7am to 7pm. Access will be maintained for emergency services and businesses on Fraser Court. We ask that you try to limit driving in/out the construction area as much as possible during the work. It is anticipate the work will be complete by Monday, August 10 weather-permitting.
July 24, 2020Asphalt Paving on Herrell Avenue and Firman Drive is anticipated to be completed by Monday, July 27. Asphalt removal on Harding Avenue will begin on Tuesday, July 28. Concrete removal and replacement as well as asphalt paving is anticipated to be completed by Friday, August 7, weather-permitting. There will be a local road closure for this work. The road will be closed from 7am to 7pm during this work; it will be opened at the end of each day. Please do not park on the street during the hours of 7am to 7pm. Access will be maintained for emergency services and residents that live on Harding Avenue. We ask that residents try to limit driving in/out the construction area as much as possible during the work. Work will not occur on the weekend. July 9, 2020Work on Mapleton Avenue is generally complete. Asphalt removal will begin on Herrell Avenue and Firman Drive starting Monday, July 13, the work is anticipated to be complete by the week of July 27, weather permitting. There will be a local road closure for this work. The road will be closed from 7am to 7pm during this work; it will be opened at the end of each day. Please do not park on the street during the hours of 7am to 7pm. Access will be maintained for emergency services and residents that live on Herrell Avenue. We ask that residents try to limit driving in/out the construction area as much as possible during the work. June 25, 2020Due to weather, the paving works were delayed on Mapleton Avenue between Ardagh Road and White Elm Road. Paving will now occur on Tuesday, June 30 and Thursday, July 2. Due to the delay this week, asphalt removal and paving on Mapleton Avenue from White Elm Road to Essa is now anticipated to be complete the week of July 6th to July 10th, weather-permitting. During the asphalt removal and paving on Mapleton, there will be no on-street parking from 7am to 7pm. Access will be provided to driveways at all times, however while work occurs in front of driveways there may be an approximate access delay of up to 30 minutes. Street parking will resume the day after the work is complete, weather-permitting. June 19, 2020Concrete work is complete on all streets except Harding Avenue. Asphalt removal is anticipated to begin Monday, June 22 on Mapleton Avenue from Ardagh Road to White Elm Road. Paving of this section is anticipated to be complete by Friday, June 26, weather depending. Asphalt removal and paving of Mapleton Avenue from White Elm Road to Essa Road is anticipated to begin the week of June 29 and expected to be complete by Monday, July 6, weather permitted. During the asphalt removal and paving on Mapleton, there will be no on-street parking from 7am to 7pm. Access will be provided to driveways at all times, however while work occurs in front of driveways there may be an approximate access delay of up to 30 minutes. Street parking will resume the day after the work is complete, weather-permitting. June 5, 2020- Work on Caplan Avenue and Cartwright Drive is generally complete.
- Concrete work on all streets except Mapleton Avenue and Harding Avenue are complete.
- Concrete work, restoration and adjustments of maintenance holes will occur onMapleton Avenue the week of June 8 to 12.
May 29, 2020Work on Barrie View Drive and Georgian Drive are generally complete.- Surface Course Asphalt on Caplan Avenue was delayed due to rain. It will be complete Monday, June 1 at night.
- Asphalt removal will begin on Cartwright Drive Monday, June 1, asphalt paving is anticipated to be completed by Friday, June 5, weather permitting. There will be a local road closure for this work. The road will be closed from 7am to 7pm during this work; it will be opened at the end of each day. Please do not park on the street during the hours of 7am to 7pm. Access will be maintained for emergency services and residents that live on Cartwright Drive. We ask that residents try to limit driving in/out the construction area as much as possible during the work.
- Concrete work will continue on Mapleton Avenue next week.
May 21, 2020Asphalt removal and asphalt replacement will begin on Sunday, May 24, 2020,Barrie View Drive and Caplan Avenue. This work will be completed at night (approximately 7pm to 7am). On Thursday, May 28, 2020, the surface asphalt work will begin at 5pm on Caplan Avenue. This will allow all the surface asphalt work to be completed in one night. It is anticipated the work will be completed by Friday, weather-permitting.- Concrete removal and replacement will continue on Herrell Avenue, Firman Avenue, Mapleton Drive, and Saunders Road next week.
- Asphalt removal and replacement is scheduled to begin on Monday, June 1, 2020Cartwright Drive. The work is anticipated to be completed by Friday, June 5, 2020, weather-permitting. There will be a local road closure for this work. The road will be closed from 7am to 7pm during this work; it will be opened at the end of each day. Please do not park on the street during the hours of 7am to 7pm. Access will be maintained for emergency services and residents that live on Cartwright Drive. We ask that residents try to limit driving in/out the construction area as much as possible during the work.
May 15, 2020- Base course asphalt was completed on Georgian Drive this week. Surface course asphalt and line painting will be completed next week on Georgian Drive. Georgian Drive will be complete by the end of next week (May 22), weather permitting.
- Concrete removal and replacement will occur on Herrell Avenue and Mapleton Avenue next week (May 19-May 22), weather permitting.
- Asphalt removal and placement is scheduled for Barrie View Drive and Caplan Avenue for the week of May 25 to May 29. This work will occur at night.
May 8, 2020- Concrete removal and replacement on Georgian Drive is complete. Asphalt removal on Georgian Drive will begin Monday, May 11. Base asphalt placement is anticipated to begin Wednesday, May 13. With top asphalt expected to be completed by May 22, weather depending.
- Concrete removal and replacement will continue on Barrie View Drive, Caplan Drive, Cartwright Drive and Herrell next week.
|