Kidd's Creek Culvert Replacement

The City of Barrie and Lake Simcoe Region Conservation Authority staff have collaborated to develop a solution to reduce the potential of flooding from Kidd's Creek at Dunlop Street.

The preferred solution is to implement an open channel designed to contain the regulatory flow. This regulatory flow is based on the Hurricane Hazel storm and is greater than the 100-year storm event.

Project Features

The Drainage Master Plan Update (2019) has confirmed the findings of previous studies of Kidd’s Creek and indicated that conveyance improvements are recommended for the section of Kidd’s Creek in the vicinity of Dunlop Street, west of Parkside Avenue. This section of Kidd’s Creek is being daylighted north of Dunlop Street and between Dunlop Street and High Street. The open watercourse solution also has significant environmental effect. Daylighting Kidd’s Creek provides opportunities to work with partners such as the Lake Simcoe Region Conservation Authority, MNRF and DFO to incorporate Low Impact Design (LID) drainage works and green infrastructure best practices to improve local storm water management issues.

Schedule

This project will take place from June 2019 till June 2022. It will be implemented in a phased manner to accommodate
in-water works windows and road closures. The project will include:

  • Relocation of gas main services to prepare for construction
  • Building Condition Assessments and Designated Substance Survey
  • Demolition of buildings on north side (formerly Knights Inn and Sticky Fingers)
    Starts August 21, 2019 and will take approximately two months.
    Knights Inn building scheduled to be demolished starting Sept. 9, 2019.
  • Construction of temporary access for Fire Hall No. 1
    Topographic survey information to assist in the design of the Fire Hall No. 1 temporary access road starts Sept. 9.
  • Project Update - October 31​, 2019
    Asphalt coring and testing for Dunlop St., High St. and Bradford St. will take place on Friday, Nov. 1. Asphalt coring requires the use of a rotary cutting tool to remove a cylindrical sample from the existing asphalt.​ If weather doesn't allow for the work to take place Friday, it will be scheduled for the week of Nov. 4. The work is anticipated to be complete within one day. There will be short duration lane closures on Dunlop St. during the work.
  • Creek Realignment north and south of Dunlop Street            
  • Sanitary and watermain relocation            
  • Utility relocation            
  • Culvert Replacement
  • Sanitary and watermian relocation            
  • Utility relocation            
  • Culvert Extension (across Bradford Street)             
  • Road paving

As the project progresses, further information will be provided.

Affected Services

Hydro, telephone, and cable TV services should not be affected by the construction, barring any unforeseen circumstances. Limited service interruptions for:

  • Sanitary sewer lateral servicing / replacement
  •  Water servicing
  • Natural gas

Curbside collection will not be affected. On their normal curbside collection day, businesses and residents are asked to place all garbage, organics, recyclables and yard waste materials at the front of the property as usual. The construction contractor will remove these items and take them to outside of the construction zone for pickup by the City’s waste contractor. Please mark your address on all of your containers.

Traffic Impacts

Vehicular traffic will be affected during construction. Advanced Notices and Detour signage will be provided.
Frequently Asked Questions
How will Fire Services be accommodated due to the road closure?

A temporary access to Bradford Street will be constructed from Fire Hall No. 1 along the former Barrie Collegiate Lands

Who is paying for this project?

The roadway improvements are part of the City’s capital plan for asset reconstruction. Grants from the Federal Government have been received to cover property and natural disaster mitigation measures, totalling $3 Million.