Skip Navigation LinksSanitary-Sewer-Relining 2021 Sanitary Sewer Relining Program

Road Construction Project, EN1184

2021 Sanitary Sewer Relining

The Sanitary Sewer Relining Program involves annual asset management activities focusing on the structural lining for sanitary sewer mains.

Impacted Streets

The work includes the structural lining of approximately 1,645m of sewer main, as well as pre-lining and post-lining CCTV inspection, maintenance hole benching and structural repairs, drop structures, and sanitary service cleanouts. Locations for Sanitary Sewer Lining 2021 Program:

  • Alexander Avenue – Johnson Street to 185 m east of Johnson Street
  • Codrington Street – Dundonald Street to Duckworth Street
  • Downsview Drive – 80m South of Napier Street to Steel Street
  • Shanty Bay Road – 250m West of Johnson Street to Johnson Street
  • Shanty Bay Road – 50m East of Johnson Street to 70 m east of Garrett Crescent
  • Napier Street – 40m West of Varden Avenue to Varden Avenue
  • Napier Street – 80m West of Downsview Drive to Downsview Drive

Schedule

May 25, 2021 Expected Start
July 2021Expected Completion

About the Sanitary Sewer Relining Program 

The Sanitary Sewer Relining Program is intended to extend the life of aging infrastructure. The sanitary sewers require upgrading to meet today’s standards, which will minimize long term maintenance costs. This will be achieved without any excavation of the roads

The wastewater collection system has traditionally been replaced or rehabilitated as part of full road reconstruction projects. While it is cost effective to do this while the roads are being constructed, it limits repairs to only sewers within road reconstruction projects. This results in many segments of the sewer collection system in need of repair being postponed, increasing the risk of failure and increasing infiltration into the sewers.

This program aims to complete sewer rehabilitation using trenchless technologies, which reduces costs by reducing road restoration requirements and will also reduce operational costs associated with repeated maintenance activities or emergency repairs.

Affected Services

Water service, Hydro, Telephone, Cable TV, and Gas services should not be affected by the construction, barring any unforeseen circumstances. 

Sanitary Service

Some temporary interruptions in the sanitary service will occur when the pipe liner material is curing. Impacted residents will receive notices of the interruptions at least a day before they are scheduled to occur.

Curbside Collection

On the normal curbside collection day, impacted residents are asked to place all garbage, organics, recyclables and yard waste materials at the front of their property as usual. It is very important that you take your refuse and recyclable items to the front of your property by 7am, otherwise these items might not be picked up. The City’s waste pickup contractor is anticipated to have access through the construction site.  If the City’s waste pickup contractor does not have access, the construction contractor will remove these items and take them to outside of the construction zone, for pickup by the City’s waste pickup contractor. Your garbage cans, organics bin and recycling boxes will be returned to your property later that day. Please mark your address on all of your containers. 

Access to Properties

All reasonable efforts will be made to maintain vehicle access to driveways.  However, there may be some temporary interruptions to access during construction while construction vehicles maneuver.  Access will be restored as quickly as possible. The Contractor will provide prior notice of any imminent access restrictions to the businesses and residents.
Pedestrian access to all homes and businesses will be maintained during construction.

Safety

The contractor is required to conduct his work in a safe manner, including working in the middle of the roadway with through traffic.  We ask that you take extra caution during the construction period to ensure everyone’s safety.

Traffic Impacts

The contractor will use traffic control measures to permit through traffic through the construction site.  Typically this will include using traffic cones to steer drivers around the contractor’s vehicles, which will frequently be parked in the centre of the roadway where sanitary maintenance structures (manholes) are. Occasionally, flag persons will be required to assist with traffic control. Access for emergency vehicles will be maintained at all times.