Skip Navigation LinksSidewalk-Infill-Program 2018 Sidewalk Infill Program

Road Construction Project

2018 Sidewalk Infill Program

The City of Barrie has tendered Contract 2018-015T for 2018 Sidewalk Infill Program – Various Locations.

This program will include construction of sidewalks to eliminate mid-block sidewalk terminations, increase sidewalk connectivity by eliminating sidewalk dead ends, and install sidewalks in locations that are not serviced to meet City service standards.

The 2018 Sidewalk Infill Program includes the construction of Sidewalks on the following streets:

  • Commerce Park Drive, 200m West of Bryne Drive to 225m South
  • Cook Street, Steel Street to 250m North
  • Millburn Street, Cumberland Street to 100m North
  • Rose Street, Newton Street to Davidson Street

Project Updates

Sept 28, 2018
Construction is generally complete. Some restoration work is still remaining and should be completed soon.

August 8, 2018
Commerce Park Drive is completed.

Project Features

  • Construction of concrete sidewalks
  • Associated restoration items including driveways and sodding

Schedule

Estimated Start: June 2018
Estimated Completion. September 2018

Affected Services

Water, sanitary, sewer, Hydro, Telephone, Cable TV, and gas services should not be affected by the construction, barring any unforeseen circumstances.

Curbside Collection: On the normal curbside collection day, residents are asked to place all garbage, organics, recyclables and yard waste materials at the front of your property as usual. The construction contractor will remove these items and take them to outside of the construction zone, for pickup by the City’s waste pickup contractor. Your garbage cans, recyclable items to the front of your property by 7 a.m. otherwise these items might not be picked up.

Access to Properties

All reasonable efforts will be made to maintain vehicle access to driveways. However, there may be some temporary interruptions to access during construction. Access will be restored as quickly as possible. The Contractor will provide prior notice of any imminent access restrictions to the businesses and residents. Pedestrian access to all homes and businesses will be maintained during construction.

Safety

The Contractor is required to conduct his work in a safe manner, including fencing of deep excavations, etc. We ask that you take extra caution during the construction period to ensure everyone’s safety.

Traffic Impacts

All road will remain open to through traffic during construction, although lane closures and restrictions can be expected in order to accommodate construction activities. We ask for your patience in such instances.