Skip Ribbon Commands
Skip to main content
Sign In

Skip Navigation LinksDunlop-Street-Bridge-Sanitary-Relocation Dunlop Street Bridge Sanitary Relocation

Road Design Project, E01-EN1469

​Dunlop Street Bridge Sanitary Relocation

Sarjeant Drive to Anne Street

To facilitate the Ministry of Transportation's (MTO) Dunlop Street Bridge Interchange project works planned for the future, the City of Barrie will be relocating the existing trunk sanitary sewer.

The existing alignment crosses Dunlop on the west side of the bridge and then crosses Highway 400 south of the bridge. The existing alignment conflicts with MTO’s future bridge structure. MTO requires the City to move the sewer so they can construct the new Dunlop Street Bridge.

The City has awarded the Engineering Design of the Dunlop Street Trunk Sanitary Relocation to Associated Engineering and is currently in the design phase of the project.

Project Scope

It has been confirmed that the scope of works will include relocating the trunk sanitary sewer along Cedar Point Drive from Dunlop to Edgehill and abandon the existing sewer abutting the Highway 400 right of way. The sewer will cross Highway 400 south of the existing interchange and connect to the existing main at Hart Drive.

   

Project Updates

June 2022

    • Subsurface Utility Deliverables provided
    • Survey Deliverables provided
    • Geotechnical investigations works are underway
    • Associated Engineering is working towards the 60% submission
Previous Updates

May 2022

  • Subsurface Utility field investigations completed
  • Topographic Survey Field Work completed
  • Geotechnical Consultant awarded
  • Associated Engineering is working towards the 60% submission.

April 2022

Associated Engineering is working towards the 60% submission.

March 2022

The City has successfully obtained T2ue to complete the Subsurface Utility Engineering for the project. As well, hired Rudy Mak to complete the topographic and boundary survey. Associated Engineering is working towards the 60% submission

February 2022

The 30% submission was delivered and comments from the City provided. Associated is working towards the 60% submission.

January 2022

30% Detailed Design package under development.​​

December 2021

30% Detailed Design package under development.​

November 2021

Associated Engineering has provided the City with design alignment options and are currently working towards the 30% design submission.​

October 2021​

Associated Engineering is completing the environmental field studies associated with the Dyments Creek Crossing. The preliminary design is currently underway.

Project Schedule

Engineering DesignOctober 2021 to December 2022
Utility RelocationJanuary 2023 to May 2023
ConstructionJune 2023 to December 2023

Frequently Asked Questions

How long is the MTO construction for the Dunlop Interchange works anticipated to take?

Unknown at this time.




Looks like your screen is a bit too small

The page you are attempting to view is not currently compatible with the dimensions of your device. Please visit this page on a larger screen.