Skip Navigation LinksGunn-Street-Reconstruction Gunn Street Reconstruction

Design Project

Gunn Street Reconstruction

This project includes the complete reconstruction of Gunn Street from Peel Street to St. Vincent Street, including new sanitary sewer, storm sewer, watermain, curb and gutter, sidewalk, and asphalt.

​​Most of the infrastructure in along Gunn St was constructed in the early to mid-1950's and is at or approaching the end of its maximum potential life.  It has experienced age-related deterioration or physical failure (watermain breaks, etc.), and is need of replacement.

This area was indentified as a candidate for full right of way reconstruction based on aggregated risk associated with surface and subsurface infrastructure.  Given the age and deteriorated condition of the infrastructure, other lifecycle strategies are not expected to signifcantly extend the existing remaining life of current assets or deliever expected service levels.  

Full reconstruction of the right of way will improve service levels to the community, allow the City to monitor the performance of the assets over time, and bundle the application of future lifecycle activies together.  This will reduce capital and operating costs in the the long term, minimixe disruption to the community, and limit environmental damages from construction. Learn about pavement management​

Project Updates

June 17, 2021: See Notice of Public Information Centre 

April 2021: Tender package is being finalized

June 2020: 90% Detailed Design package is complete

Public Information Centre (PIC)

Due to the COVID-19 restrictions on gatherings, we did have an in person Public Information Centre, however staff wanted to ensure your questions are answered. Please view presentation slides. A virtual PIC was held on Wednesday, June 23, 2021, from 4pm to 7pm to discuss the project, and a comment sheet was available to submit comments by email until June 30, 2021.

Project Features

  • Replacement of the sanitary sewer and sanitary service laterals up to property line
  • Replacement of the watermain, water services and curb stop to the property line
  • Installation of a storm sewer system 
  • Reconstruction of the roadway including base & surface course asphalt, granular road base and curb and gutter
  • Concrete sidewalk on the north side only 
  • Boulevard regrading and restoration
  • Traffic Management Plan to minimize traffic disruptions

Schedule 

Public Information Centre
Please view the Public Notice for full details
June 23, 2021
Utility Relocations  2021
​Construction Phase 1*
Gunn Street from Davidson Street to Peel Street
​Spring 2022 to Fall 2022 

​​Construction Phase 2*
Gunn Street from Davidson Street to St. Vincent Street
​​Spring 2023 to Fall 2023
​Finish​December 2023, with some possible restoration in Spring 2024
* Pending budget approval, utility relocations and permitting