2017 Asphalt Resurfacing

Project budget is $4.55M and expected completion date is September 2017. Asphalt resurfacing including concrete curb and sidewalk repairs on the following streets:

2016 Contract:

  • Bayfield (north city limits to Livingstone Street) Completed
  • Burbank Pl. (St. Vincent to cul-de-sac) Completed
  • Hurst Dr. (Golden Meadow to Big Bay Point) Completed
  • Johnson Street from Georgian Drive to Hickling Trail Completed
  • St. Vincent St. (Bell Farm to Codrington) Completed

2017 Contract 1:

  • Anne St. (Edgehill to Sunnidale) Completed
  • Cundles Rd & Access Rd (Leacock to Sunnidale) Completed
  • Ferndale Dr. (North City Limits to Benson) Completed
  • Ferris Lane (Bayfield to Collete) Completed
  • Mapleview Dr. (20th Sideroad to 650m east of Prince William Way Completed
  • Worsley St. (Bayfield to Mulcaster) Completed

2017 Contract 2:

  • Mapleview Dr. (Bryne Drive to 130m west of Reid Drive)  Completed
  • Veterans Dr (Mapleview to Caplan)  Completed

The asphalt surface of the noted streets has deteriorated with patches, multiple cracks and some rutting. The primary purpose of the asphalt road resurfacing works is to repair and improve the ride quality of the various roads and prevent the roads from deteriorating to the point that they would require more extensive and costly rehabilitation and/or reconstruction.

Many of the existing maintenance holes and catch basins need structural repairs and adjustments to ensure proper surface water drainage and a safe and smooth driving surface around these structures.

The removal and replacement of some of the concrete curbs and sidewalks will be undertaken to resolve deterioration or unsafe conditions. When curb or sidewalk is removed and replaced in front of existing driveways, a small strip of driveway will be sawcut, removed and restored with new asphalt.

Project Updates

October 2, 2017

2017 Contract 1:  Asphalt and concrete works are completed on all streets. The Contractor is completing restoration and deficiencies on all streets and should be completed by mid-October.

September 18, 2017

2017 Contract 1: Asphalt works are completed on all streets but Ferndale with a small amount of work remaining at Cloughley and Ferndale intersection.  Restoration work including driveways, sidewalks, line painting, boulevard and topsoil and sod work is on-going and should be completed by the end of September.

2017 Contract 2: All works are completed

September 5, 2017

2016 Contract: All works are completed

2017 Contract 1:

  • Concrete and Asphalt work on Anne Street from Sunnidale Road to Letitia Street is completed. Concrete and asphalt work on Anne Street from Shirley Avenue to Edgehill Drive will be completed by September 15, weather dependent. Resurfacing of Anne Street from Letitia to Shirley will no longer be completed as part of the 2017 Asphalt Resurfacing Program – Contract 1. The City of Barrie plans to install watermain in this section of Anne Street in the near future. To avoid digging up the resurfaced road for the watermain work, this section will not be resurfacing this year and will be resurfaced after the watermain work is completed.
  • Concrete and asphalt work from Cundles Road from Leacock to Anne is completed. Cundles Road from Anne to Sunnidale will be completed by September 15, weather dependent.
  • Concrete work has begun on Ferris Lane. Concrete work on Ferndale Drive will begin at the end of the week. Asphalt grinding and paving is expected to begin September 11 on Ferris Lane and Ferndale Drive.
  • Concrete and asphalt works on Mapleview and Worsley are completed.

2017 Contract 2: Concrete and asphalt works are completed on Mapleview Drive and Veterans Drive. Traffic loops and line painting (stop bars and pedestrian cross walks) will be completed by September 8, 2017, weather dependent.

August 18, 2017

2016 Contract:
Asphalt works are completed. 

2017 Contract 1:

  • Concrete and Asphalt work on Mapleview and Worsley are complete
  • Cundles Road is generally completed with a small section of road to be paved during the Anne Street paving works
  • Anne Street concrete work is nearly completion. The asphalt works will begin soon and should be completed by the end of August.
  • Work on Ferris Lane from Bayfield to Collete and Ferndale Drive from north City limits to Benson is expected to begin in September.

2017 Contract 2:

Concrete work is on-going. Asphalt works are expected to begin at the end of August. This work is being completed at night between the hours of 8:00pm and 7:00am with some concrete work occurring between 7:00am and 10:00am. 

July 27, 2017

2016 Contract: Asphalt works on St. Vincent are now complete. Top course asphalt on Burbank Place will be completed on Friday, July 28

2017 Contract 1:

  • Asphalt removal and replacement on Cundles Rd from Leacock to Sunnidale has begun. The paving works on Cundles are expected to be completed by August 4.
  • Concrete work is on-going on Worsley Street from Mulcaster to Bayfield. Asphalt removal and replacement is expected to begin on Tuesday, August 8.
  • Concrete work on Anne Street from Edgehill to Sunnidale will continue through August. Paving works is expected to begin late August.
  • Work on Ferris Lane from Bayfield to Collete and Ferndale Drive from north City limits to Benson is expected to begin in September.

2017 Contract 2: Concrete works are expected to begin July 31.  It is expected that this work will be completed during the night between the hours of 8:00 pm and 7:00 am. Some of the concrete work may occur during the hours of 7:00 am to 10:00 am, there will be some single lane closures for the concrete work. Asphalt works will begin once the concrete work is completed.

July 5, 2017

Concrete removal and replacement works have begun on Cundles. Asphalt removal on Mapleview Drive East is completed, paving is scheduled for July 6 and driveway paving on July 7.

Concrete works on Mapleview Drive (Bryne Drive to 130m west of Reid Drive) and Veterans Drive (Mapleview Drive to Caplan Avenue) are expected to begin mid-July and asphalt works will begin in August, weather dependent. It is expected that these works will be completed during the hours of 8pm to 7am.

June 26, 2017

Asphalt resurfacing is completed on Bayfield Street, Hurst Drive and Johnson Street. Concrete works are completed on Burbank Place and St. Vincent Street. Base asphalt is completed on Burbank place. Asphalt removal and resurfacing for St. Vincent Street is expected to begin at the beginning of July, weather dependent.

June 5, 2017

Top Course Asphalt on Hurst Drive is expected to be completed by June 9 (weather dependent). Line painting will immediately follow the asphalt works. Concrete works on St. Vincent Street and Burbank Place are on-going and should be completed within 2 weeks (weather dependent). Asphalt works will follow the concrete works.

Project Features

  • Removal and replacement of some of the existing concrete curbs where necessary;
  • Removal and replacement of some of the existing concrete sidewalk where necessary;
  • Adjustment of existing frames and grates on catch basins including some replacements;
  • Adjustment of existing frames and grates on maintenance holes including some replacements
  • Adjustment of existing water valve boxes to grade including some replacements:
  • Removal of existing asphalt (partial and some full depth);
  • Supply and placement of hot mix asphalt;
  • Reinstatement of any traffic signal loops;
  • Reinstatement of any pavement markings;
  • Boulevard restoration (topsoil and seed/sod); and,
  • Driveway restoration.

Traffic Impacts

All roads will remain open to through traffic during construction, although lane closures and restrictions can be expected in order to accommodate construction activities.  We ask for your patience in such instances.

Affected Services

Water, sanitary sewer, Hydro, telephone, Cable TV, and gas services should not be affected by the construction, barring any unforeseen circumstances.

Garbage Collection: On the normal curbside collection day, place all garbage, organics, recyclables and yard waste materials at the front of your property as usual.  The construction contractor will remove these items and take them to outside of the construction zone, for pickup by the City’s waste pickup contractor. Your garbage cans, organics bin and recycling boxes will be returned to your property later that day.  Please mark your address on all of your containers. It is very important that you take your refuse and recyclable items to the front of your property by 7:00 a.m. otherwise these items might not be picked up.

Access to Properties

All reasonable efforts will be made to maintain vehicle access to driveways.  However, there may be some temporary interruptions to access during construction.  Access will be restored as quickly as possible.

The Contractor will provide prior notice of any imminent access restrictions to the businesses and residents.

Pedestrian access to all homes and businesses will be maintained during construction.

Safety

The contractor is required to conduct his work in a safe manner, including fencing of deep excavations, etc.  We ask that you take extra caution during the construction period to ensure everyone’s safetyA: