Stormwater & Creeks Projects

The water quality of Lake Simcoe and its tributaries is fundamental to the quality of life we enjoy in Barrie. The City has a responsibility to mitigate flooding and protect bodies of water from any harmful stormwater runoff.

Stormwater or creeks projects that require major long-term road closures are listed under road design & construction projects.

Sediment Removal Maintenance Projects Underway
Expected
Duration
​​Ferndale Drive South Stormwater Management Pond Sediment Removal Maintenance
To reduce the potential for flooding in the surrounding area and to reduce the risk of sediment and other contaminants entering the Bear Creek Wetland, a sensitive environment that the pond serves to protect.

​June to September 2021

Hewitt's Creek Stormwater Management Facility Routine Maintenance Work
The HW08 stormwater management facility is located at 107 Prince William Way. 

July to December 2021​
​Lovers Creek Stormwater Management Facility Routine Maintenance Work

The LV01 stormwater management facility is located at 211 Hurst Drive. 

​July to December 2021
Lovers Creek Stormwater Management Facility Routine Maintenance Work

The LV23 stormwater management facility is located at Stunden Lane and Patrick Drive.​

​July to December 2021
​Whiskey Creek Stormwater Management Facility Routine Maintenance Work             

The WK04 stormwater management facility is located at Minet’s Point Road and Hurst Drive​.

​July to December 2021
Design & Construction Projects Underway
Expected
Construction

​​Bunkers Creek Culvert Replacements & Watercourse Improvement
To increase capacity for Innisfil Street and Bradford Street culvert crossings and watercourse improvements from Innisfil Street to Lakeshore Drive.

​2023–2024

Dyments Creek Culvert Replacements & Watercourse Improvement
To increase capacity for Sanford Street and Bradford Street culvert crossings and watercourse improvements from Sanford Street to downstream of Bradford Street

​2023–2024

JC Massey Way Emergency Stormwater Pond Repair
Reconstruction of the pond with a 600mm clay liner.

2021

​​Kidd’s Creek Marina Sediment Removal
Sediment with measures to meet environmental regulations.

​2022

Kidd’s Creek Pond Improvements
Retrofit and upgrade of the Sunnidale Stormwater Management Facility.

2021

Lovers Creek Channel Rehabilitation
Rehabilitation works.

​2023–2024

Lovers Creek Stormwater Management Facility Retrofit
Repair and restoration of the creek and the online pond from Highway 400 to Bayview Dr.

​2021

MacMorrison Park Stormwater Retrofit
Exploration of alternatives to provide an engineered flood control feature in MacMorrison Park.

​n/a

Sophia Creek Culvert Replacement
Replacement of the existing culverts that convey Sophia Creek under Grove Street East.

​2021
Sophia Creek Stormwater Management Pond Upgrades

Retrofit/ upgrade the Currie Storm water management facility.

​2022