Hotchkiss Creek Improvements | Barrie-Collingwood Railway to Tiffin

Project Type
Stormwater & Creeks
Project #
EN1396
Status
In Progress
Estimated Completion
2029

The City is undertaking improvements to Hotchkiss Creek between the Barrie-Collingwood Railway (BCRY) and Tiffin Street. Improvements incorporated into the project have been identified in the City’s Drainage Master Plan

The project includes replacing the deteriorated culvert that is beneath the BCRY, which extends toward Tiffin Street, with a larger structure to increase conveyance capacity and  reduce the risk of potential flooding. The project will include enhancement to the natural habitat of the creek at either end of the culvert.

Project Updates

September 18, 2023

The City has purchased the property at 47 Alfred Street as part of the creek improvements and to facilitate stormwater improvements within the Allandale neighbourhood. The City has retained a contractor to demolish the buildings on the property and restore the lands to grass, which is scheduled to start later this month.

Project Features

The project will:

  • Provide storage during large storm events to reduce storm flows downstream of the project
  • Improve conveyance capacity at the Barrie-Collingwood Railway culvert
  • Improve watercourse quality by providing opportunities for habitat in Hotchkiss Creek

Schedule

Project StageTiming
Design2022–2028
Property Acquisition 2026–2027
Utility relocations2028
Construction2029