Project Type
Roads
Underground Infrastructure
Project #
EN1585
Status
In Progress
Estimated Completion
TBD
An existing 600mm watermain along Ferndale Drive between Harvie Road and Tiffin Street has been out of service since 2017 due to operational issues. Through investigations, it was determined there were some leaks in the pipe. This project will repair these leaks and return the watermain to service. The project will include:
- Excavation and repair of watermain at leak locations
- Installation of air release chamber for watermain
- Restoration of curb, sidewalk and road as necessary
Project Updates
August 21, 2026
Construction will commence the week of August 24, 2026. Lane shifts on Ferndale Drive will be in place at the watermain repair locations throughout construction. Temporary sidewalk closures will also be required within the construction areas, with marked pedestrian detours.
Schedule
| Anticipated Design Completion | Winter 2026 |
|---|---|
| Anticipated Construction | August–November 2026 |