Project Type
Roads
Underground Infrastructure
Project #
EN1585
Status
In Progress
Estimated Completion
December 2026
An existing 600mm watermain along Ferndale Drive between Harvie Road and Tiffin Street has been out of service since 2017 due to operational issues. Through investigations, it was determined there were some leaks in the pipe. This project will repair these leaks and return the watermain to service. The project will include:
- Excavation and repair of watermain at leak locations
- Installation of air release chamber for watermain
- Restoration of curb, sidewalk and road as necessary
Project Updates
November 24, 2026
Construction is ongoing, with lane shifts expected to remain in place until December 23, 2026. Two of the five repairs have been completed, with work ongoing at a third location. Backfilling of the completed repair areas is also underway, with restoration work planned for the coming weeks. Work at the remaining two repair locations is scheduled to begin in early December.
Schedule
| Anticipated Design Completion | Winter 2026 |
|---|---|
| Anticipated Construction | August–December 2026 |