Project Type
Roads
Project #
EN1271
Status
In Progress
Estimated Completion
Spring 2026
The City is installing a raised median on Mapleview Drive East, from Dean to Goodwin. The work is being completed by the contractor, Guild Electric Limited, and follows the recommendations from the Hewitt’s Secondary Plan Municipal Class Environmental Assessment (EA).
The raised median was presented to the public during the EA process and is part of the recommended design to improve safety, traffic flow, and access in support of future growth in the Hewitt’s Secondary Plan area.
The timing of the project is connected to the construction of the new public school at Mapleview Drive and Dean Avenue. With the school expected to open in 2027, it’s important to complete nearby traffic improvements in advance.
Schedule
| Stage | Timing |
|---|---|
| Anticipated Construction | November–December 2025 |
| Final Restorations | Spring 2026 |