This new infrastructure project supports growth and development near the McKay Rd and Veteran’s Dr intersection in south-west Barrie.
The project extended along McKay Rd from east of Veteran’s Dr to west of the future Reid Dr extension and along Veteran’s Dr from south of McKay, northerly to Salem Rd. The project included roadway expansion on McKay Rd including intersection improvements at McKay and Veteran’s, and new watermains, and sanitary sewers along McKay Rd and Veteran’s Dr.
Project Updates
July 4, 2024
The road reopened at 1:50pm on July 4, 2024.
Project Details
This project was the first phase of new infrastructure expansion to support development north and south of McKay Rd in the Salem Secondary Plan Area. Through this construction project water and wastewater service were extended south from Salem Rd along Veteran’s Dr, then westerly along McKay Rd.
Additionally, with the significant residential development planned, the project enhances McKay Rd by widening the roadway, adding new concrete sidewalks, a raised cycle track, and local stormwater management improvements. The road improvements also include intersection expansion and an upgraded McKay and Veteran’s intersection.
Public Information Centre (PIC)
Public notice was completed in the form of newspaper ads and mailed Notice Letters to affected residents. McKay Road and Veteran’s Drive Improvements PIC Presentation was posted on the City’s YouTube Channel and the Presentation Slides were also available for review.
Project Features
The project included the following detailed scope of work:
- Closure of McKay Rd from 1km west of Veteran’s Dr to east of Hwy 400
- Closure of Veteran’s Dr from Salem Rd to 9th Line of Innisfil
- Closure of the McKay Rd and Veteran’s Dr intersection
- New 500mm diameter transmission watermain on Veteran’s Dr from Salem Rd to McKay Rd
- New 400mm local waterm ain on McKay Rd from Veteran’s Dr westerly to future Reid Dr
- New 1200mm deep trunk sanitary sewer installed by trenchless construction from Veteran’s to future Reid Dr
- Road widening to four (4) traffic lanes and a centre median/turning lane along McKay Rd and through the Veteran’s Dr intersection
- McKay Rd urban streetscape including curbs, sidewalks, a cycle track, street lighting, traffic signals, landscaping, and stormwater management infrastructure.

Project Schedule
Estimated Construction Start: | March 2022 |
Construction Completion: | July 2024 |