Upgrades within Mapleton Park were completed as part of the Pavement Management Program (road segments in the Cundles neighbourhood). The contract was awarded to Lisbon Paving Co. Limited. This work was part of City Council’s approved 2025 budget and aligns with Council’s strategic plan to update and improve City Infrastructure.
Project Updates
April 29, 2026
Sand has been added in the parkette and additional grass seeding has been planted. Fencing around Mapleton Park is scheduled to be removed on May 4, at which time the park will be open to the public.
Project Details
Upgrades included:
- Removal of the existing asphalt pathway and interlocking brick
- Installation of a new, widened asphalt pathway
- Removal and localized repairs of the existing concrete playground curb
- Installation of new, concrete sidewalk ramps and tactile plates