The annual Pavement Management Program includes resurfacing roads, which mainly involves the repair of defects, such as cracks, and rutting found in the top layers of the road. The goal is to proactively prevent roads from deteriorating to the point they would require more extensive and costly rehabilitation, and/or reconstruction. Approximately 18.4 kilometres of roadway is being resurfaced in 2026.
There are competing priorities and a limited budget. To determine road segment priority, pavement candidates are compared to each other to determine criticality based on a number of different criteria. See pavement management FAQs.
Asphalt crack sealing and pavement holding strategies are completed separately from the annual Pavement Management Program.
2026 Road Segments & Project Updates
The below road segments have been confirmed for resurfacing in 2026. Due to the size of the program, the 2026 work has been split up into sub-projects.
In addition to the listed road segments, permanent speed cushions were installed on Madelaine Drive as part of this program.
Cundles Neighbourhood
Construction in the Cundles neighbourhood area is being completed by Lisbon Paving Co. Limited. An April 2026 info bulletin was distributed to impacted residents.
July 3, 2026
Work on Coles Street is complete.
June 10, 2026
Concrete repairs, and asphalt roadway removal and replacement are complete. Boulevard restorations, including driveway apron repairs are scheduled to start the week of June 15.
May 13, 2026
The contractor has begun localized concrete curb and sidewalk repairs. Residents will be notified in advance if access to their driveway will be impeded. Work is expected to be complete by the end of the week.
Asphalt removal and replacement is currently scheduled to start in late June with full completion scheduled for August 2026.
April 29, 2026
Concrete curb and sidewalk repairs will commence at the beginning of May (weather pending). Once concrete repairs are complete on all impacted roads in the Cundles neighbourhood, asphalt roadway removal and replacement will commence.
July 3, 2026
Work on Craig Crescent is complete.
June 10, 2026
Concrete repairs, and asphalt roadway removal and replacement are complete. Boulevard restorations, including driveway apron repairs are scheduled to start the week of June 15.
May 13, 2026
The contractor is schedule to start localized concrete curb and sidewalk repairs the week of May 19. Residents will be notified in advance if access to their driveway will be impeded. The work is expected to take approximately two to five days.
Asphalt removal and replacement is currently scheduled to start in late June with full completion scheduled for August 2026.
April 29, 2026
Concrete curb and sidewalk repairs will commence at the beginning of May (weather pending). Once concrete repairs are complete on all impacted roads in the Cundles neighbourhood, asphalt roadway removal and replacement will commence.
July 3, 2026
Boulevard restorations, including driveway apron repairs are complete. Asphalt roadway removal and base asphalt replacement are rescheduled to start in late July, in coordination with ongoing utility upgrade works being completed in the same area. Surface course asphalt is scheduled to be completed by the end of August.
June 10, 2026
Concrete repairs are complete. Boulevard restorations, including driveway apron repairs are scheduled to start the week of June 22. Asphalt roadway removal and replacement is currently scheduled to start late June with full completion schedule for August 2026.
May 13, 2026
Concrete curb and sidewalk repairs are underway in the remaining areas of the Cundles Neighbourhood. Asphalt removal and replacement is currently scheduled to start mid-June with full completion scheduled for August 2026.
April 29, 2026
Concrete curb and sidewalk repairs were completed in November 2025. Asphalt road removal was unable to happen in 2025 due to the early arrival of snow. Once concrete repairs are complete on all impacted roads in the Cundles neighbourhood this spring, asphalt roadway removal and replacement will commence.
July 3, 2026
Utility work under a separate contract is ongoing in this area. As a result, further concrete and boulevard restorations are required. Asphalt roadway removal and base asphalt replacement are rescheduled to start in late July, in coordination with ongoing utility upgrade works being completed. Surface course asphalt is scheduled to be completed by the end of August.
June 10, 2026
Concrete repairs are ongoing. Boulevard restorations, including driveway apron repairs, will follow. Asphalt removal and replacement is currently scheduled to start in mid-July with full completion scheduled for August 2026.
May 13, 2026
As part of a separate project, electrical utility upgrades are ongoing on this street. Upgrades are scheduled to be completed mid-June at which time localized concrete curb and sidewalk repairs will begin.
Asphalt removal and replacement is currently scheduled to start in early July with full completion scheduled for August 2026.
April 29, 2026
Concrete curb and sidewalk repairs will commence this spring (specific timing TBD). Once concrete repairs are complete on all impacted roads in the Cundles neighbourhood, asphalt roadway removal and replacement will commence.
July 3, 2026
Boulevard restorations, including driveway apron repairs are rescheduled to start the week of July 13. Asphalt roadway removal and base asphalt replacement are rescheduled to start in late July, in coordination with ongoing utility upgrade works being completed in the same area. Surface course asphalt is scheduled to be completed by the end of August.
June 10, 2026
Concrete repairs are complete. Boulevard restorations, including driveway apron repairs are expected to start the week of June 22. Asphalt removal and replacement is currently scheduled to start in early July with full completion scheduled for August 2026.
May 13, 2026
The contractor is scheduled to start removing and replacing the full length of concrete curb on Hilderbrand Court starting the week of May 19. Residents have been notified that access to their driveways will be interrupted and received instructions as to where they can park while the work is taking place. The work will take approximately three to five days.
Asphalt removal and replacement is currently scheduled to start in late June with full completion scheduled for August 2026.
April 29, 2026
Concrete curb and sidewalk repairs will commence this spring (specific timing TBD). Once concrete repairs are complete on all impacted roads in the Cundles neighbourhood, asphalt roadway removal and replacement will commence.
July 3, 2026
Utility work under a separate contract is ongoing in this area. As a result, further concrete and boulevard restorations are required. Asphalt roadway removal and base asphalt replacement are rescheduled to start in late July, in coordination with ongoing utility upgrade works being completed. Surface course asphalt is scheduled to be completed by the end of August.
June 10, 2026
Concrete repairs are ongoing. Boulevard restorations, including driveway apron repairs, will follow. Asphalt removal and replacement is currently scheduled to start in early July with full completion scheduled for August 2026.
May 13, 2026
Concrete curb and sidewalk repairs are underway in the remaining areas of the Cundles Neighbourhood. Asphalt removal and replacement is currently scheduled to start mid-June with full completion scheduled for August 2026.
April 29, 2026
Concrete curb and sidewalk repairs were completed in November 2025. Asphalt road removal was unable to happen in 2025 due to the early arrival of snow. Once concrete repairs are complete on all impacted roads in the Cundles neighbourhood this spring, asphalt roadway removal and replacement will commence.
July 3, 2026
Concrete repairs are complete. Boulevard restorations, including driveway apron repairs, are expected to start the week of July 13. Asphalt roadway removal and base asphalt replacement are rescheduled to start at the end of July, in coordination with ongoing utility upgrade works being completed in the same area. Surface course asphalt is scheduled to be completed by the end of August.
June 10, 2026
Concrete repairs are ongoing. Boulevard restorations, including driveway apron repairs, will follow. Asphalt removal and replacement is currently scheduled to start in early July with full completion scheduled for August 2026.
May 13, 2026
As part of a separate project, electrical utility upgrades are ongoing on this street. Upgrades are scheduled to be completed mid-June at which time localized concrete curb and sidewalk repairs will start.
Asphalt removal and replacement is currently scheduled to start in early July with full completion scheduled for August 2026.
April 29, 2026
Concrete curb and sidewalk repairs will commence this spring (specific timing TBD). Once concrete repairs are complete on all impacted roads in the Cundles neighbourhood, asphalt roadway removal and replacement will commence.
July 3, 2026
Boulevard restorations, including driveway apron repairs, are complete. Asphalt roadway removal and base asphalt replacement are rescheduled to start in late July, in coordination with ongoing utility upgrade works being completed in the same area. Surface course asphalt is scheduled to be completed by the end of August.
June 10, 2026
Concrete repairs are complete. Boulevard restorations, including driveway apron repairs are scheduled to start the week of June 22. Asphalt roadway removal and replacement is currently scheduled to start in early July with full completion schedule for August 2026.
May 13, 2026
The contractor is scheduled to start removing and replacing the full length of concrete curb on this section of Oren starting the week of May 25. Residents will be notified that access to their driveways will be interrupted and received instructions as to where they can park while the work is taking place. The work will take approximately two weeks.
Asphalt removal and replacement is currently scheduled to start in late June with full completion scheduled for August 2026.
April 29, 2026
Localized repairs of concrete sidewalks were completed in November 2025. The City's infrastructure team has approved the full length removal of the concrete curbs in this area. This work will begin in spring 2026 (specific timing TBD), followed by full depth removal and replacement of the asphalt roadway, driveway aprons and final boulevard restorations.
July 3, 2026
Utility work under a separate contract is ongoing in this area. As a result, further concrete and boulevard restorations are required. Asphalt roadway removal and base asphalt replacement are rescheduled to start in late July, in coordination with ongoing utility upgrade works being completed. Surface course asphalt is scheduled to be completed by the end of August.
June 10, 2026
Concrete repairs are ongoing. Boulevard restorations, including driveway apron repairs, will follow. Asphalt removal and replacement is currently scheduled to start in mid-July with full completion scheduled for August 2026.
May 13, 2026
The contractor is schedule to start localized concrete curb and sidewalk repairs the week of May 25. Residents will be notified in advance if access to their driveway will be impeded. The work will take approximately five to ten days.
Asphalt removal and replacement is currently scheduled to start in early July with full completion scheduled for August 2026.
April 29, 2026
Concrete curb and sidewalk repairs will commence this spring (specific timing TBD). Once concrete repairs are complete on all impacted roads in the Cundles neighbourhood, asphalt roadway removal and replacement will commence.
July 3, 2026
Work on Coles Street is complete.
June 10, 2026
Concrete repairs, and asphalt roadway removal and replacement are complete. Boulevard restorations, including driveway apron repairs are scheduled to start the week of June 15.
May 13, 2026
The contractor has started localized concrete curb and sidewalk repairs. Residents will be notified in advance if access to their driveway will be impeded. The work is expected to be complete by the end of the week.
Asphalt removal and replacement is currently scheduled to start in late June with full completion scheduled for August 2026.
April 29, 2026
Concrete curb and sidewalk repairs will commence at the beginning of May (weather pending). Once concrete repairs are complete on all impacted roads in the Cundles neighbourhood, asphalt roadway removal and replacement will commence.
For questions about this work, please contact Jenny Rae, Engineering Contract Administrator, at jenny.rae@barrie.ca or 705-739-4220 x4444.
Downtown & North Barrie
The contract has been awarded to GIP Paving Incorporated. Info bulletins have been distributed to properties impacted by the downtown resurfacing:
Additional information bulletins will be distributed to impacted properties as details are confirmed.
July 14, 2026
Asphalt and restoration works are now completed.
June 16, 2026
Work is generally complete. Line painting and minor restoration work continue.
June 11, 2026
The contractor has rescheduled surface asphalt paving to Friday, June 12, 9pm–7am, weather permitting. A road closure will be in place and there will be no parking allowed on the street during this work. Details will be available at barrie.ca/RoadClosures.
June 10, 2026
The contractor has rescheduled surface asphalt paving to Thursday, June 11, 9pm–7am, weather permitting. A road closure will be in place and there will be no parking allowed on the street during this work. Details will be available at barrie.ca/RoadClosures.
June 5, 2026
Surface asphalt is now scheduled to take place Wednesday, June 10, 9pm–7am, weather permitting. A road closure will be in place and there will be no parking allowed on the street during this work. Details will be available at barrie.ca/RoadClosures.
June 1, 2026
Concrete work is generally complete. Interlock restorations are expected to be completed the week of June 1. Surface asphalt is anticipated to occur June 11 and 12, 9pm–7am, weather permitting. A road closure will be in place for this work. Details will be available at barrie.ca/RoadClosures.
May 21, 2026
Concrete work continued on Bayfield Street this week. Asphalt removal was completed this week and base asphalt will be completed by the end of the week, weather permitting.
May 15, 2026
Overnight closures of Bayfield Street (Sophia to Dunlop and Dunlop to Simcoe) are scheduled for May 18 to 22, as well as June 11 and 12, to allow crews to complete asphalt removal and replacement. Bayfield Street will be closed nightly, 9pm–7am, reopening each morning. The Dunlop Street intersection will remain open throughout the closures.
Detours will be in place during the closures. Road closure details will be available at barrie.ca/RoadClosures and transit impacts are posted at MyRideBarrie.ca/news.
May 11, 2026
Concrete work is now expected to begin the week of May 11. Localized parking closures will occur during the concrete work.
Asphalt removal is anticipated to begin on Bayfield Street the week of May 19. This work will occur at night and there will be daily closures between 9pm and 7am for this work. Detours will be in place during the closure. The road will reopen each morning. Road closure details will be available at barrie.ca/RoadClosures.
May 1, 2026
Concrete work is expected to begin the week of May 4. Localized parking closures will be in place where concrete work is occurring.
Work to commence in 2026. Please stay tuned for details.
July 17, 2026
Work is complete.
July 14, 2026
Concrete and asphalt work are complete. The remaining work includes traffic sensor installation and activation.
June 16, 2026
Work is generally complete. Line painting and minor restoration work continue.
June 11, 2026
The contractor has rescheduled surface asphalt paving to Thursday, June 11, 9pm–7am, weather permitting. A road closure will be in place and there will be no parking allowed on the street during this work. Details will be available at barrie.ca/RoadClosures.
June 10, 2026
The contractor has rescheduled surface asphalt paving to Friday, June 12, 9pm–7am, weather permitting. A road closure will be in place and there will be no parking allowed on the street during this work. Details will be available at barrie.ca/RoadClosures.
June 5, 2026
Asphalt removal on is still scheduled to take place Sunday, June 7, 9pm–7am, weather permitting.
Surface asphalt is now scheduled to only take place on Thursday, June 11, 9pm–7am, weather permitting.
Road closures will be in place and there will be no parking allowed on the street during the work. Details will be available at barrie.ca/RoadClosures.
June 1, 2026
Concrete work is generally complete. Interlock restorations are expected to be completed the week of June 1.
Asphalt removal is anticipated to occur June 7, 9pm–7am, weather permitting. Surface asphalt is anticipated to occur June 11 and 12, 9pm–7am, weather permitting. Road closures will be in place for this work. Details will be available at barrie.ca/RoadClosures.
May 21, 2026
Concrete removal and replacement is expected to begin on Monday, May 25 and be completed by the end of the week.
May 1, 2026
Concrete work is expected to begin the week of May 4. Localized parking closures will be in place where concrete work is occurring.
July 17, 2026
Work is complete.
July 14, 2026
Concrete and asphalt work are complete. Traffic sensor installation and activation remain outstanding.
June 16, 2026
Work is generally complete. Line painting and minor restoration work continue.
June 11, 2026
The contractor has rescheduled surface asphalt paving to Thursday, June 11, 9pm–7am, weather permitting. A road closure will be in place and there will be no parking allowed on the street during this work. Details will be available at barrie.ca/RoadClosures.
June 10, 2026
The contractor has rescheduled surface asphalt paving to Friday, June 12, 9pm–7am, weather permitting. A road closure will be in place and there will be no parking allowed on the street during this work. Details will be available at barrie.ca/RoadClosures.
June 5, 2026
Surface asphalt is now scheduled to only take place on Thursday, June 11, 9pm–7am, weather permitting. A road closure will be in place and there will be no parking allowed on the street during this work. Details will be available at barrie.ca/RoadClosures.
June 1, 2026
Concrete work is generally complete. Asphalt removal was completed and base asphalt has been placed. Interlock restorations are expected to be completed the week of June 1.
Surface asphalt is anticipated to occur June 11 and 12, 9pm–7am, weather permitting. A road closure will be in place for this work. Details will be available at barrie.ca/RoadClosures.
May 21, 2026
Concrete work continued on Collier Street this week.
Asphalt removal is expected to be completed on Sunday, May 24. Collier Street will be closed between 9pm and 7am for this work.
There will be daily overnight closures, 9pm–7am, the week of May 24–29 to complete base asphalt (weather permitting). There will be no parking on Collier Street during this time. For transit detour details, visit MyRideBarrie.ca/news.
May 11, 2026
Concrete work is now expected to begin the week of May 11. Localized parking closures will occur during the concrete work.
May 1, 2026
Concrete work is expected to begin the week of May 4. Localized parking closures will be in place where concrete work is occurring.
July 31, 2026
The first layer of base asphalt is compelted. The second layer of base asphalt is anticipated to be completed Friday, August 7 and Saturday, August 8, weather permitting. Surface asphalt is anticipated to be completed the week of August 17, weather permitting.
July 24, 2026
Asphalt removal and base asphalt was completed between Bayfield Street and Janine Street. Asphalt removal and base asphalt between Janine Street and St. Vincent Street will be completed the week of July 27, weather permitting.
July 17, 2026
Asphalt removal is expected to take place Monday, July 20 and Tuesday, July 21, starting at Bayfield and moving towards St. Vincent. Base asphalt is anticipated to be completed Friday, July 24, weather permitting.
July 14, 2026
Concrete work is complete. Asphalt removal and paving are expected to begin the week of July 20.
June 25, 2026
Concrete curb and sidewalk work is anticipated to begin the week of July 6.
Work to commence in 2026. Please stay tuned for details.
July 31, 2026
All work is complete.
July 24, 2026
Asphalt works are completed. Line painting will be completed shortly.
July 17, 2026
- Surface asphalt has been completed between Bayfield and Kozlov.
- Surface asphalt between Kozlov and Anne is anticipated to be completed on Monday, July 20, weather permitting.
- Surface asphalt between Anne and Sunnidale is anticipated to be completed on Tuesday, July 21, weather permitting.
July 14, 2026
Concrete work is complete. Base-course asphalt paving and driveway restorations are nearing completion. Surface-course asphalt paving is expected to be completed by the week of July 20.
June 25, 2026
Asphalt removal and base asphalt placement will continue the week of June 29.
June 19, 2026
Concrete work is generally complete. Asphalt removal is anticipated to begin Monday, June 22, with base asphalt to be placed where asphalt has been removed by Friday, June 26, weather permitting.
June 16, 2026
Concrete curb and sidewalk work has begun.
July 14, 2026
Asphalt and restoration works are completed.
July 17, 2026
Work is complete.
July 14, 2026
Concrete and asphalt work are complete. The remaining work includes traffic sensor installation and activation.
June 25, 2026
Surface course asphalt is scheduled for Tuesday, June 30, weather permitting.
June 19, 2026
Base asphalt placement has been completed.
June 16, 2026
Asphalt removal is underway. Asphalt placement is anticipated to be completed by June 19, weather permitting.
July 31, 2026
Concrete curb and sidewalk work is on-going. Asphalt removal and base asphalt is anticipated to begin the week of August 10, weather permitting.
For questions about this work, please contact Sony Sukumaran, Contract Administrator, Egis Group, at sony.mukhil-sukumaran@egis-group.com or 647-212-1544.
Letitia Heights & South Barrie
The contract has been awarded to IPAC Paving Limited. A May 2026 info bulletin was distributed to nearby properties.
July 17, 2026
Work is complete.
July 14, 2026
Surface asphalt paving is complete between Mapleview and Lockhart. The remaining work includes final pavement markings.
June 25, 2026
Surface asphalt between Saunders and Mapleview is expected to be completed the week of June 29, weather permitting.
June 1, 2026
Asphalt removal is now complete and base asphalt has been placed. Surface asphalt and driveway repairs are anticipated to be completed this week.
May 21, 2026
Concrete work is expected to begin on Monday, May 25, and the work will occur during daytime hours.
Asphalt removal will also begin Monday, May 25, occurring between 7pm and 7am. Base asphalt is expected to be completed by the end of the week, which will also be night work.
May 11, 2026
Concrete work on is expected to begin the week of May 25.
July 23
Concrete curb and sidewalk work is anticipated to begin the week of July 27 and continue for a few weeks, weather permitting.
July 23
Concrete curb and sidewalk work is anticipated to begin the week of July 27 and continue for a few weeks, weather permitting.
July 23
Concrete curb and sidewalk work is anticipated to begin the week of July 27 and continue for a few weeks, weather permitting.
July 23
Concrete curb and sidewalk work is anticipated to begin the week of July 27 and continue for a few weeks, weather permitting.
July 31, 2026
- Fairview to Huronia & Yonge to Hurst: Surface asphalt is complete with the exception of the section on Little Avenue from Hurst Drive to approximately 70 m past the tracks. This section will be completed at a later date due to Metrolinx permitting and requirements.
July 23, 2026
- Bayview to Huronia & Yonge to Metrolinx Limits: Surface asphalt is planned for Monday, July 27, weather permitting.
July 17, 2026
- Fairview to Bayview: Work is complete.
- Bayview to Huronia: Base asphalt has been completed. Surface asphalt is anticipated to be completed the week of July 27.
- Yonge to Hurst: Asphalt removal has been completed. Base asphalt is scheduled to be completed, Wednesday, July 22, weather permitting. The section Little Avenue from Hurst to approximately 70 m past the tracks will be completed at a later date due to Metrolinx permitting and requirements.
July 6, 2026
- Bayview to Huronia: Asphalt removal has begun. Base asphalt is anticipated to be completed by the end of the week.
- Yonge to Hurst: Concrete curb and sidewalk work has begun.
June 25, 2026
- Fairview to Bayview: Surface asphalt is expected to be completed the week of June 29, weather permitting.
- Bayview to Huronia: Concrete curb and sidewalk work is expected to begin the week of June 29.
June 19, 2026
Concrete work is generally complete. Asphalt removal is anticipated to begin Monday, June 22, with base asphalt to be placed by Friday, June 26, weather permitting.
June 16, 2026
Concrete curb and sidewalk work is continuing this week.
June 1, 2026
Concrete work is anticipated to begin the week of June 8.
For questions about this work, please contact Sony Sukumaran, Contract Administrator, Egis Group, at sony.mukhil-sukumaran@egis-group.com or 647-212-1544.
2025 Carryover Road Segments & Status
The 2025 Pavement Management Program construction activities finished for the season in mid-December. Work on some roads was unable to be finished in 2025 due to the early arrival of snow. A December 2025 info bulletin and an April 2026 info bulletin were distributed to impacted residents. Outstanding work was completed between May and July 2026, as outlined below.
June 12, 2026
Asphalt and restoration works are now completed.
June 1, 2026
Surface asphalt work is scheduled to be completed by June 5, weather permitting.
April 29, 2026
The top layer of asphalt and sod restorations are scheduled to take place in May 2026.
July 16, 2026
All work is complete.
June 12, 2026
Restorations are expected to be completed this month.
June 1, 2026
Asphalt works are now completed. Restorations are expected to be completed this week.
May 29, 2026
Asphalt removal and replacement, along with sod restorations are scheduled to take place in May 2026.
June 12, 2026
Restorations are now completed.
June 1, 2026
Asphalt works are now completed. Restorations are expected to be completed this week.
April 29, 2026
Asphalt removal and replacement, along with sod restorations are scheduled to take place in May 2026.
June 12, 2026
Restorations are now completed.
June 1, 2026
Asphalt works are now completed. Restorations are expected to be completed this week.
April 29, 2026
The top layer of asphalt and sod restorations are scheduled to take place in May 2026.
June 12, 2026
Asphalt and restoration works are now completed.
June 1, 2026
Surface asphalt work is scheduled to be completed by June 5, weather permitting.
April 29, 2026
The top layer of asphalt and sod restorations are scheduled to take place in May 2026.
For questions about this work, please contact Jennifer Whittley, Engineering Contract Administrator, at Jennifer.Whittley@barrie.ca or 705-726-4242 x4935.
What to Expect During Construction
You may experience inconveniences such as dust, noise, and short delays. The City will make efforts to reduce impacts, and your patience is appreciated.
Pedestrian access will be maintained during construction. All roads will remain open to traffic, except Bayfield Street, Clapperton Street and Collier Street, which will be closed during construction from 9pm to 7am and opened daily.
The contractor will use traffic control measures, such as traffic cones to steer through traffic around contractor equipment and vehicles, within the construction site. Flag persons will assist with traffic control, if required.
Access to homes and businesses will be maintained. Access for emergency vehicles will always be maintained.
Vehicle entry to properties within the construction limits will be available. At times, direct access to driveways will be interrupted for curb/sidewalk replacement and driveway restoration. Residents will be notified of driveway access disruptions one day in advance of the disruption.
Parking on roadways in an active construction area is not permitted. Vehicles parked in the construction zone will be ticketed and towed.
Construction will affect Barrie Transit routes, and schedules. Changes to bus routes in the construction area will be posted in advance. Transit notices are posted at MyRideBarrie.ca/News.
Hydro, sanitary sewer services, water services, telephone, cable TV, and gas services should not be affected by the construction, barring any unforeseen circumstances.
Waste collection will occur on your regular collection day during construction. Ensure everything for pick up is curbside by 7am (4:30am in the downtown BIA) on the collection day or it may not be picked up.
Asbestos in Asphalt
As part of the construction work, the City must test the asphalt for asbestos before starting work. Tests have identified asbestos is present in the asphalt on:
- Gloria Street (entire street)
- Oren Boulevard (Heather to Gloria and Gloria to Gloria)
- Noam Drive (entire street)
- Heather Street (Oren to Kozlov)
- Hilderbrandt Court (entire street)
The asbestos levels found are significantly below the level of concern set by the Ministry of Labour. The risk of exposure to asbestos for workers and bystanders is low. As a precaution, the City contractor will follow these steps while removing the contaminated asphalt:
- Wet the pavement during asphalt cutting, grinding, and removal;
- Attach dust collecting devices, with HEPA filters, to equipment when possible;
- Provide personal protective equipment, such as disposable coveralls and respirators, to on-site workers upon request; and
- Transport asphalt containing asbestos to a provincially approved disposal site.
Although the risk is very low for public exposure, residents can choose to keep their doors and windows closed and leave the area during the time asphalt cutting and removal occurs. This is usually one or two days during the project. As a safety measure, do not pick up loose pieces of asphalt from the roadway. Learn more about asbestos in asphalt.
Frequently Asked Question
The following streets were resurfaced in 2025:
- Argyle Road, Coulter to Glenwood
- Birchwood Drive, Springdale to Stanley
- Burton Avenue, William to Milburn
- Collete Crescent, Ferris to Daphne
- Cundles Road East, St. Vincent to Livingstone
- Daphne Crescent, Collete to Cundles
- Eccles Street South/Perry Street, all
- Glenwood Drive, Cundles to Bayfield
- Golfdale Road, Coulter to Glenwood
- Hart Drive, Dunlop to John
- Huronia Road, Loon to #400 Huronia
- Innisfil Street, Perry to Vespra
- Janine Street, Daphne to Cundles
- Mapleview Drive East, eastbound left turn lane onto Welham & a section of the east bound lanes between Welham and Huronia
- Mapleview Drive West, Essa to County Rd 27
- Nelson Street, Napier to College
- Twiss Drive, Mapleview to Wessenger
- Virgilwood Crescent, Deerpark to Springdale
- Wall Court, all
- Wellington Street West, Bayfield to Anne
In addition to the listed road segments, upgrades within Mapleton Park were completed in 2025 as part of this program.
