Mapleton Park Pavement Upgrades

Project Type
Parks & Forestry
Project #
EN1549
Status
Recently Completed

Upgrades within Mapleton Park were completed as part of the Pavement Management Program (road segments in the Cundles neighbourhood). The contract was awarded to Lisbon Paving Co. Limited. This work was part of City Council’s approved 2025 budget and aligns with Council’s strategic plan to update and improve City Infrastructure.

Project Updates

April 29, 2026

Sand has been added in the parkette and additional grass seeding has been planted. Fencing around Mapleton Park is scheduled to be removed on May 4, at which time the park will be open to the public.

Project Details

Upgrades included:

  • Removing the existing asphalt pathway and interlocking brick
  • Installing a new, widened asphalt pathway
  • Removing and repairing the existing concrete playground curb 
  • Installing new, concrete sidewalk ramps and tactile plates