Bear Creek Wetland: Kierland & Marta Backyard Regrading

Project Type
Other
Project #
EN1513
Status
In Progress
Estimated Completion
TBD

Residents on Marta Crescent and Kierland Road have experienced persistent standing water along the rear of their properties over the past several years. These residential lots back onto a section of the Bear Creek Wetland, located north of Summerset Drive, which is designated as a Provincially Significant Wetland. To mitigate the risk of future flooding of the residents' backyards, this project will regrade the affected rear yards adjacent to the wetland. 

Project Updates

July 16, 2026

Phase 2 will start in August 2026. The work will include placing fill in the backyards of 19–43 Marta Crescent and 51–57 Kierland Road, and removing the temporary sandbag cofferdam. A July 2026 info bulletin is being distributed to impacted residents.

Project Phasing

The project has been phased as follows.

Phase 1
(Completed Work) 
  • Install temporary cofferdam & dewatering measures along rear of Marta Crescent backyards. 
  • Objective: Provide short-term flood relief for Marta residents.
Phase 2
(Current Work)
  • Place fill in the backyards of Marta Crescent and Kierland Road residential lots that are adjacent to the Bear Creek Wetland and remove the temporary sandbag cofferdam. 
  • Objective: Provide long-term flood relief for Marta and Kierland Residents.
Phase 3
(Future Work)
  • Bear Creek Wetland Channel Restoration and BR09 SWM Facility restoration. 
  • Objective: Provide a long-term solution to elevated water levels in the Bear Creek Wetland and restore the functionality of the BR09 SWM Facility
Phase 4
(Future Work)
  • Upstream Watercourse Erosion Mitigation. 
  • Objective: Complete a geomorphic assessment of the upstream Bear Creek watercourse system within the Ardagh Bluffs to identify and complete erosion mitigation projects. The purpose of the projects is to reduce the amount of sediment being generated from the active erosion sites and deposited into the Bear Creek wetland. Reducing upstream erosion will extend the lifespan of the wetland channel and reduce future maintenance of the channel and the BR09 SWM Facility outlet structure.

Phase 2 Scope & Limits

To prevent future flooding into the residents' backyards of 19–43 Marta Crescent and 51–57 Kierland Road, the following work will be completed: 

  • Removing temporary sand bag cofferdam 
  • Removing replacing chain-link fence
  • Removing and reinstating side yard fence where required
  • Backyard regrading (fill) to existing flood elevations
  • Tree removals and replacement as required
  • Various backyard feature removal and reinstatement as required

The contract has been awarded to Buildscapes Construction Ltd.

Phase 2 Schedule

  • Design: 2025
  • Construction: August–December 2026

Impacted Services

Services such as Bell, Rogers, Enbridge and Alectra should not be affected. 

Traffic Impacts

Traffic impacts are expected to be minimal.

Access to Properties 

All reasonable efforts will be made to maintain vehicle access to driveways. However, there may be some temporary interruptions to access during construction. Access will be restored as quickly as possible. Advanced notification will be provided to property owners prior to any driveway access restriction. Pedestrian access will be maintained during construction.