Duckworth Street Improvements & Grove Street East Watermain

Project Type
Roads
Sewers & Watermains
Stormwater & Creeks
Project #
EN1166 & EN1355
Status
Recently Completed

This three-phase project reconstructed Duckworth Street from Bell Farm Road to St. Vincent Street and also included a new watermain on Grove Street from Duckworth Street to Nelson Street. The project was a major infrastructure investment that improves road safety, active transportation, and critical underground services in Barrie’s east end. 

The Duckworth Street work included new watermain, sewer replacements, and right-of-way improvements including, new sidewalks, new pavement, intersection upgrades, and road widening for bicycle lanes. The Grove Street work included new watermain, pavement and bicycle lanes.

This project was initiated in 2014 as a Class environmental assessment study to evaluate alternatives for implementing bike lanes and improved active transportation on Duckworth Street. The results of the EA were carried through into detailed design, which also included replacement of aging underground infrastructure and other infrastructure improvements.

Project Updates

August 26, 2025 

Final pavement markings, including the new bike lanes on Duckworth Street and Grove Street East, are now complete, officially marking the project's completion. The City thanks local residents, businesses, and visitors for your patience and support throughout construction.

Project Features

Project highlights include:

  • New watermain and sanitary sewer replacements
  • Stormwater upgrades to improve drainage
  • Road widening and new dedicated bike lanes
  • New sidewalks, curbs, and fresh pavement
  • Intersection upgrades, including new permanent traffic signals at Codrington and Duckworth

Due to the poor condition of Duckworth Street pavement, construction was split into three phases.

Schedule | Phases 2 & 3

Construction for phase 2 commenced together with phase 3. The majority of the work for phases 2 and 3 was done in 2023 and 2024. The project was substantially complete at the end of 2024 and final paving top lift asphalt was completed in summer 2025. 

Construction for phase 1 (Duckworth Street, Melrose Avenue to St. Vincent Street) was completed in 2019. The above schedule applied to phases 2 and 3.
Detail Design Complete:Fall 2021
Property Acquisition:2021–2022
Utility Relocations:2021–2022
Anticipated Construction:2023–2025