Mapleton Park Pavement Upgrades

Project Type
Parks & Forestry
Project #
EN1549
Status
Upcoming

Upgrades within Mapleton Park will be completed as part of the Pavement Management Program (road segments in the Cundles neighbourhood). The contract was awarded to Lisbon Paving Co. Limited. This work is part of City Council’s approved 2025 budget and aligns with Council’s strategic plan to update and improve City Infrastructure.

Mapleton Park will be closed October 14 to November 15 to accommodate the work. A September 2025 information bulletin was distributed to nearby residents. 

Upgrades include:

  • Removal of the existing asphalt pathway and interlocking brick
  • Installation of a new, widened asphalt pathway
  • Removal and localized repairs of the existing concrete playground curb 
  • Installation of new, concrete sidewalk ramps and tactile plates

What to Expect During Construction

  • Inconveniences may occur such as, dust, noise, and short delays. The City will make efforts to reduce impacts, and your patience is appreciated. 
  • Pedestrian access along local roads, adjacent to the park, will be maintained during construction. 
  • Mapleton Park will be closed October 14, 2025, to November 15, 2025. 
  • Local roads will be open to traffic at all times, barring any unforeseen circumstances. Access for emergency vehicles will always be maintained. 
  • The Contractor is required to conduct work in a safe manner, such as using traffic cones and fencing off excavations. Please use extra caution around the construction zone to ensure everyone’s safety.