Huronia Road Watermain Lining | Big Bay Point to Little

Project Type
Underground Infrastructure
Project #
EN1559
Status
In Progress
Estimated Completion
Fall 2027

This project includes lining 1,400 metres of an existing 500 mm diameter concrete pressure pipe watermain on Huronia Road between Big Bay Point Road and Little Avenue due to deterioration.

Assessments have identified corrosion and deterioration on parts of the large watermain, which presented risk of significant failures. As part of a proactive approach to maintaining infrastructure, the City will line this watermain to prevent future issues.

This work helps extend the life of the watermain, supports reliable water service, and reduces the risk of emergency repairs and disruptions in the future. 

Project Updates

October 6, 2026

The contractor has completed excavating the access pits required for the watermain lining work. Crews are cleaning the existing watermain to prepare for the new liner installation.

The new 500 mm watermain installation at Big Bay Point Road is scheduled to begin in the coming weeks. Lining the existing pipe will occur concurrently. Construction is anticipated to be completed by the end of November 2026, followed by temporary roadway and boulevard restorations.

To facilitate this work, the northbound lane of Huronia Road remains closed. Traffic is restricted to southbound travel only from Little Avenue. Businesses along Huronia Road remain open and accessible throughout construction. For closure and detour information, visit barrie.ca/RoadClosures.

Project Phases

Phase 1: Lining Big Bay Point Drive to Herrell Avenue
Work includes: Water service transfers between Herrell Avenue and Little (required prior to lining activities), small open cut watermain section (Big Bay Point Road to 30 m north), lining and watermain commissioning.

Phase 2: Lining Herrell Avenue to Little Avenue
Work includes: Lining and watermain commissioning.

Schedule

WorkTiming
Phase 1 ConstructionSpring–Late fall 2026
Phase 2 ConstructionSpring–Late fall 2027

What to Expect During Construction

A construction site showing a dug out trench with a long white pipe reaching from the trench into the back of a truck.
Huronia Road Watermain Lining Project, April 2026