This project includes lining 1,400 metres of an existing 500 mm diameter concrete pressure pipe watermain on Huronia Road between Big Bay Point Road and Little Avenue due to deterioration.
Assessments have identified corrosion and deterioration on parts of the large watermain, which presented risk of significant failures. As part of a proactive approach to maintaining infrastructure, the City will line this watermain to prevent future issues.
This work helps extend the life of the watermain, supports reliable water service, and reduces the risk of emergency repairs and disruptions in the future.
Project Updates
October 6, 2026
The contractor has completed excavating the access pits required for the watermain lining work. Crews are cleaning the existing watermain to prepare for the new liner installation.
The new 500 mm watermain installation at Big Bay Point Road is scheduled to begin in the coming weeks. Lining the existing pipe will occur concurrently. Construction is anticipated to be completed by the end of November 2026, followed by temporary roadway and boulevard restorations.
To facilitate this work, the northbound lane of Huronia Road remains closed. Traffic is restricted to southbound travel only from Little Avenue. Businesses along Huronia Road remain open and accessible throughout construction. For closure and detour information, visit barrie.ca/RoadClosures.
Project Phases
Phase 1: Lining Big Bay Point Drive to Herrell Avenue
Work includes: Water service transfers between Herrell Avenue and Little (required prior to lining activities), small open cut watermain section (Big Bay Point Road to 30 m north), lining and watermain commissioning.
Phase 2: Lining Herrell Avenue to Little Avenue
Work includes: Lining and watermain commissioning.
Schedule
| Work | Timing |
|---|---|
| Phase 1 Construction | Spring–Late fall 2026 |
| Phase 2 Construction | Spring–Late fall 2027 |