Pavement management programs focus on applying the right pavement maintenance strategy to the right road, at the right time. A holding strategy is a reactive approach to pavement management.
Roads applicable to holding strategies generally have proposed construction phases in future years of the Capital Plan. Relatively minor investments are made to hold the road over until the full reconstruction project takes place.
Information bulletins are mailed to impacted residences and businesses ahead of construction, providing information specific to the impacted street.
Road Segments
- 5–6 Side Road (Penetanguishene Road to approximately 500 m east)
- Berczy Street (Gunn to Penetang)
- Davidson Street (Grove to Gunn)
- Newton Street (Grove to Gunn)
Old 2nd Road South (Sutton Heights to approximately 400 m south)
Project Updates
October 22, 2026
- Berczy Street, Davidson Street and Newton Street: Remaining boulevard restoration and deficiency work is ongoing. Additional asphalt driveway repairs are scheduled throughout the neighbourhood during the week of November 2. All remaining work is expected to be completed by November 13.
- Old 2nd Road South (Sutton Heights to approximately 400 m south): Stormwater management improvements and asphalt road paving are complete. Final restoration work is ongoing, with all work expected to be completed by the end of October.
- 5–6 Side Road (Penetanguishene Road to approximately 500 m east): Asphalt road paving, new pavement markings and granular shouldering are complete. Installation of a new traffic sensor in the westbound lane at Penetanguishene Road remains scheduled. Final boulevard restoration and all remaining work are expected to be completed by the end of October.
2024 Pavement Holding Strategies Deficiency Repairs
October 28, 2026
Deficiency repairs will be completed on Essa Road, Anne Street, and within the Brock and Grove Park Neighbourhoods under Contract 2024-082T. The work will begin in November and continue into December 2026 (subject to change).
The original resurfacing work was completed by GIP Inc. in October 2024. A deficiency in the concrete used has caused premature deterioration in some locations. Affected curb and sidewalk sections will be removed and replaced at the contractor's expense.
The work is scheduled on portions of Essa Road, Anne Street, Parkdale Crescent, Northpark Road, Oak Street, Victoria Street, Robert Street, John Street, Dufferin Street, Creswick Court and Bennet Road. Driveways and boulevards impacted by the repair work will also be restored.
An October 2026 information bulletin is being distributed to impacted residents, which includes the impacted road segments, details on what to expect and more.