Huronia Road Watermain Lining | Big Bay Point to Little

Project Type
Underground Infrastructure
Project #
EN1559
Status
In Progress
Estimated Completion
Fall 2027

This project includes lining 1,400 metres of an existing 500 mm diameter concrete pressure pipe watermain on Huronia Road between Big Bay Point Road and Little Avenue due to deterioration.

Assessments have identified corrosion and deterioration on parts of the large watermain, which presented risk of significant failures. As part of a proactive approach to maintaining infrastructure, the City will line this watermain to prevent future issues.

This work helps extend the life of the watermain, supports reliable water service, and reduces the risk of emergency repairs and disruptions in the future. 

Project Updates

October 22, 2026

Cleaning and video inspection of the existing 500 mm CPP watermain are complete, and the new liner has been installed between Big Bay Point Road and Herrell Avenue.

Crews are now installing the 500 mm closure pieces within the access pits along the completed section. Once this work is complete, the shoring will be removed, the excavations will be backfilled and temporary roadway restoration will follow.

The contractor continues to complete the remaining watermain lining between Herrell Avenue and Little Avenue. Extended work hours are required to complete this section, and work may continue into the evening. The City has approved the use of a watermain lining truck during the evening work. The truck operates using a generator that produces a low humming sound. No other noise-producing equipment is planned for use during the evening work. A notice of evening work has been distributed to affected residents advising of the extended work hours. This project is exempt from the Noise By-law per Schedule 2, Permanent Exemptions, Section 3: “The operations of equipment in conjunction with the City projects or reconstruction projects, general maintenance and emergency maintenance projects.”

To accommodate construction, the northbound lane of Huronia Road remains closed, with traffic restricted to southbound travel from Little Avenue. Access to roads and driveways will be maintained, and businesses along Huronia Road remain open and accessible throughout construction. For closure and detour information, visit barrie.ca/RoadClosures.

Project Phases

Phase 1: Lining Big Bay Point Drive to Herrell Avenue
Work includes: Water service transfers between Herrell Avenue and Little (required prior to lining activities), small open cut watermain section (Big Bay Point Road to 30 m north), lining and watermain commissioning.

Phase 2: Lining Herrell Avenue to Little Avenue
Work includes: Lining and watermain commissioning.

Schedule

WorkTiming
Phase 1 ConstructionSpring–Late fall 2026
Phase 2 ConstructionSpring–Late fall 2027

What to Expect During Construction