Huronia Road Watermain Lining | Big Bay Point to Little

Project Type
Underground Infrastructure
Project #
EN1559
Status
In Progress
Estimated Completion
Fall 2027

This project includes lining 1,400 metres of an existing 500 mm diameter concrete pressure pipe watermain on Huronia Road between Big Bay Point Road and Little Avenue due to deterioration.

Assessments have identified corrosion and deterioration on parts of the large watermain, which presented risk of significant failures. As part of a proactive approach to maintaining infrastructure, the City will line this watermain to prevent future issues.

This work helps extend the life of the watermain, supports reliable water service, and reduces the risk of emergency repairs and disruptions in the future. 

Project Updates

May 14, 2026

  • On April 2, 2026, the project contract was awarded to Fer-Pal Construction Limited. 
  • The contractor is scheduled to begin mobilizing equipment and materials to the site starting the week of May 19. During the first week, crews will complete exploratory work, including locating existing utilities and underground infrastructure.
  • Beginning the week of May 25, work will focus on installing new residential water services along Huronia Road between Herrell and Little. This work is anticipated to be completed by mid-June.
  • Following completion of the residential services, the contractor will proceed with installing the new watermain and commercial services between Big Bay Point and Herrell.
  • During the initial phase of construction, motorists can expect localized, short-duration lane restrictions along Huronia Road.
  • For more information, please refer to the May 2026 information bulletin that has been distributed to nearby residents and businesses. 

Project Phases

Phase 1: Lining Big Bay Point Drive to Herrell Avenue
Work includes: Water service transfers between Herrell Avenue and Little (required prior to lining activities), small open cut watermain section (Big Bay Point Road to 30 m north), lining and watermain commissioning.

Phase 2: Lining Herrell Avenue to Little Avenue
Work includes: Lining and watermain commissioning.

Schedule

WorkTiming
Phase 1 ConstructionSpring–Late fall 2026
Phase 2 ConstructionSpring–Late fall 2027

What to Expect During Construction

A construction site showing a dug out trench with a long white pipe reaching from the trench into the back of a truck.
Huronia Road Watermain Lining Project, April 2026