June 30, 2026
City staff are working with the contractor to extend construction hours to help finish the work sooner and reduce impacts on residents. This could help improve traffic flow, detours, commute times, and access to the GO Station. More details will be shared once they are confirmed.
May 27, 2026
Major culvert replacement works will require a full road closure on Mapleview Drive East between Chef Lane and Royal Jubilee Drive/Lally Terrace. The closure is expected to be in place from June 8 to November 20, 2026. Detour signage will be installed in advance. Road closure and detour details will be available at barrie.ca/RoadClosures.
Transit routes using Mapleview Drive East will be detoured during the road closure. Signage will be posted in advance. A complimentary shuttle service will be provided on both sides of the closure, ensuring continued access to the Barrie South GO Station and Maple Ridge Secondary School. View the transit notice for full details.
A May 2026 info bulletin is being delivered to nearby residents and businesses.
April 30, 2026
Construction activities continue to progress along Mapleview Drive East. Over the past month, storm sewer installation on the north side of Mapleview between Hewitt’s Creek and Chef Lane has been completed. Crews are currently constructing the stormwater management pond, located approximately 200 metres east of Chef Lane.
The next major stage of work will involve culvert installation at Hewitt’s Creek. Mapleview Drive East, from Chef Lane to Royal Jubilee Drive/Lally Terrace is expected to be closed starting in June. Please check back on this page for future updates regarding road closures and construction impacts.
March 25, 2026
Construction activities are ongoing. Over the next month, construction will include earth excavation, and installation of storm sewers along the north side of Mapleview Drive East between Kneeshaw Drive and Lally Terrace.
You can expect to see increased construction activity in the area, including equipment and truck traffic. Minor traffic delays may occur from time to time; however, every effort will be made to keep disruptions to a minimum and maintain access to homes and businesses.
February 4, 2026
A January 2026 info bulletin has been distributed to nearby properties. The contractor has retained the services of GPM Environmental (GPM) to complete a precondition survey of the exterior and interior of all properties within the project limit. Residents should expect a letter from the City and GPM to book a pre-condition survey appointment.
December 16, 2025
The contract has been awarded to Primrose Contracting Inc. Construction is now anticipated to begin in early 2026. Please check back on this page for future updates regarding road closures and construction impacts.
November 27, 2025
The City's construction tender has closed and will be awarded soon. Construction is anticipated to begin in December. Please check back for future updates about road closures and construction impacts.
November 7, 2025
Due to unforeseen delays in the tender process, the start of main construction along Mapleview Drive East has been postponed. Construction is now anticipated to begin in late 2025/early 2026.
Once more information is available and timelines are confirmed with the successful contractor, updated details will be shared on this page.
Utility relocations along Mapleview Drive East remain ongoing and are now expected to be completed in early 2026.
September 30, 2025
Utility relocations along Mapleview Drive East are ongoing and are expected to be completed this fall.
The tender for the main construction along Mapleview Drive East is open and will close in mid-October 2025. Pending award of the contract, construction is expected to begin in November 2025, with completion expected in spring 2028.
June 23, 2025
Utility relocations along Mapleview Drive East are well underway and are expected to be completed by early fall 2025.
The tender process for the main construction is expected to open in July and close in early August.
Construction is scheduled to begin in fall 2025, with project completion anticipated by spring 2028.
November 7, 2024
The project timeline has been revised. The construction package is estimated to be available on bids and tenders early next year, and construction is scheduled to begin in summer 2025.
September 17, 2024
As part of the preparation work for the upcoming construction, there will be a full closure of Mapleview Drive East between Yonge Street and Prince William Way on September 18 and 19. Alectra Utilities and their subcontractors require the closure from 9am to approximately 2pm each day. No through traffic will be allowed. View the road closure map for detour details.
September 4, 2024
The City has received the 100% submission drawing package from the consultant and anticipates the final revisions being completed by mid-September. The construction package will be available on bids and tenders this month.
July 23, 2024
The City has divided construction into two phases. The first phase is anticipated to start this September and will focus on the improvements to the Yonge Street and Mapleview Drive East signalized intersection. The second phase is anticipated to start in May 2025 and will construct the remaining works for the road improvements. Construction is being split into phases to allow the necessary time to obtain the Metrolinx permit without delaying the overall project schedule. Utility relocations are ongoing.
May 16, 2024
Enbridge Gas relocations are complete, and Alectra relocations is still underway. Once Alectra's relocations are complete Bell and Rogers will follow suit.
March 4, 2024
- Property acquisitions are complete.
- Utility relocations are underway with Alectra and Enbridge out on site. These works will continue until June/July 2024. Then, Bell and Rogers will follow with their relocations.
- Construction cannot start until the utility relocations are complete and all necessary permits are obtained. The construction schedule is being reviewed. Depending on permits and status of utility relocations, construction may begin in spring 2025.
December 12, 2023
- Completion of design by January 2024
- Property acquisitions are anticipated to be complete in early 2024
- Utility relocations to commence in Q1 2024
- Construction is still expected to start in 2024
May 23, 2023
- Completion of design by November 2023
- Property acquisitions are almost complete
- Coordination with Metrolinx, residents and other stakeholders is ongoing
- Utility relocations to commence in late 2023
- Construction to start in 2024
November 2022
- Completion of design by January 2023
- Property acquisitions are ongoing
- Coordination with Metrolinx, residents and other stakeholders is ongoing
- Utility relocations to commence in 2023
June 2022
The City is in progressing with the design of this project and has completed the 90% Design submission. Property acquisitions are underway as the City prepares for utility relocations in 2023 and construction to start in 2024.