Codrington Street & Lakeview Crescent Reconstruction

Project Type
Roads
Sewers & Watermains
Status
In Progress
Estimated Completion
2028

The design project is underway for the reconstruction of:

  • Codrington Street, Duckworth to Nelson
  • Lakeview Crescent, Codrington to Rodney 
  • Highland Avenue, Cook to Codrington

Work includes asphalt and sidewalk reconstruction, the replacement of the sanitary and stormwater infrastructure, watermains and includes replacement of underground services to the property line.

The project will renew the life of the deteriorating roadway and underground services in the area as well as increase the water network capacity for the area for future growth of the city. The project will expand and upgrade the storm and sanitary sewer networks to meet City standards.

Project Updates

July 22, 2025

Design is progressing. Field investigations are continuing, which include subsurface utility engineering, geotechnical investigation, and streetlight photometric studies.

Schedule

StageTiming
Design2021–2026 
Utility Relocations2026
Construction2027–2028

Project Features

  • Road reconstruction
  • Watermain replacement
  • Sanitary sewer and lateral replacement
  • Storm sewer installation
  • Sidewalk installation / replacement
  • Street lighting Improvements
  • Possibility for Low Impact Development 

Low Impact Development Opportunities

In an effort to reduce the quantity & improve the quality of stormwater runoff, the City of Barrie is considering implementing green infrastructure in this project. If you are interested in having stormwater friendly designs in your boulevard or interested in learning more about low impact development opportunities please contact Julia Vanderkuylen, Engineering Project Manager, at 705-739-4220 x4449 or Julia.Vanderkuylen@barrie.ca.