Project #: EN1482
September 2, 2025
Driveway and boulevard restorations are complete. Minor site cleanup remains. The Lockhart Road Resurfacing is deemed Substantially Complete as of August 22, 2025.
August 18, 2025
Driveway restorations are scheduled to be completed August 20–21. Roadway shouldering is scheduled for August 22. Final pavement markings to follow. Weather pending, all work is on track to be complete by August 22.
August 11, 2025
Top asphalt has been completed on Lockhart Road. Driveway and boulevard restorations are scheduled to begin this week. Final pavement markings are expected to be completed this week. Weather pending, all work should be complete by August 22.
August 1, 2025
Roadway repairs, base asphalt and concrete works are complete. Top asphalt is scheduled for Friday, August 8, with driveway and boulevard restorations to follow.
Intermittent lane closures and temporary restrictions are required, however full access is maintained for residents, emergency services and transit.
July 25, 2025
Roadway repairs were delayed due to utility upgrades along Lockhart Road, which were unrelated to the project. The road base repairs commenced July 23 and will be followed by base asphalt placement, concrete island construction, top asphalt placement, line painting, and driveway and boulevard restorations. This work is expected to take approximately three weeks to complete.
Intermittent lane closures and temporary restrictions are required, however full access is maintained for residents, emergency services and transit.
June 9, 2025
The City has awarded the contract for the pavement replacement work on Lockhart Road from Finsbury to approximately 100m west of the Yonge intersection, to Lisbon Paving Co. (Lisbon). The work will include concrete curb and sidewalk repairs, as well as pavement replacement.
The contractor began concrete repairs on Finsbury Street and Greer Street today and the work is expected to be complete June 13.
Asphalt roadway repairs and replacement is scheduled to begin the week of June 23 and will take approximately two weeks to complete. This includes driveway and boulevard restorations.
A June 2025 information bulletin was distributed to nearby residences and businesses.