Bayview Drive Transportation Improvements

Project Type
Road Construction
Status
In Progress
Estimated Completion
2026

The City of Barrie Transportation Master Plan identified Bayview Drive as key transportation corridor and recommended several transportation improvements to accommodate growth in Barrie to 2031. 

This project includes road widening, cycle tracks, sidewalk work, new watermains and stormwater work on Bayview Drive between Little and Big Bay Point. The work also includes resurfacing on Bayview Drive from Little to Springhome.

View current road closure on map

Project Updates

September 17, 2024

Resurfacing works between Springhome Drive and Little Avenue were completed ahead of the first day of school. Storm sewer work and watermain work have continued in front of Allandale Recreation Centre and Innisdale Secondary School. Watermain will continue to be constructed south in the coming weeks. Storm sewer work in front of 230 Bayview continues.  Twin box culverts have been connected to the existing structure. Dewatering has begun around the twin box culvert south of 330 Bayview ahead of watermain construction under the box culvert.

Project Features

The Big Bay Point Road intersection at Bayview Drive was part of the Harvie Road/Highway 400 Crossing project, completed in June 2021. The improvements to Bayview Drive will match the improvements that were constructed at the intersection, and will continue north to Little Avenue.

The design improvements include:

  • Two 3.5 lanes – one each northbound and southbound
  • Continuous 4.2m two-way left turn lane
  • Off-road cycle tracks on both sides of the roadway where possible*
  • Accessible 1.8m sidewalk on the west side of the roadway
  • Replacement and improvement to local water and sanitary sewer services
  • Stormwater culvert crossing upgrades
  • Stormwater quantity and quality improvements
  • Street lighting upgrades

*This project was redesigned for off-road cycle tracks as much as possible. The dedicated off-road cycle tracks could not be fully achieved throughout the corridor due to property, utility, public transit requirements, existing rec centre parking, and conflicting use constraints. 

Schedule

2018–2020Undertaking of detailed design and preparation of Tender Ready documents
2021–2022Property Acquisition
2023–2024Utilities
2024Construction Start
2026Construction End
Final asphalt will be placed in 2026. Most construction is expected to be complete in 2025.

Access to Businesses/Organizations

Area businesses and organizations will remain open during construction, and drivers and pedestrians will be directed safely through the construction zone to access local businesses, Innisdale Secondary School, Allandale Recreation Centre, and other organizations in the area. 

Image
Detour in effect as of August 2, 2024. The road closure allows for one lane of continuous, one-way traffic southbound on Bayview Drive. Bayview Drive is only accessible from Little (there is no access to Bayview from Big Bay Point).


Affected Services

Barrie Transit

Construction will affect Barrie Transit routes and schedules. Changes to bus routes in the construction area will be posted in advance and details will be available at MyRideBarrie.ca/News

Water Services

Water services will be shut off for short durations of the construction to allow for connection to the new watermain. At least 48-hours notice will be provided to property owners and businesses prior to any water shutoffs.

Curbside Collection

Curbside collection materials will be collected on the regular collection day during construction. Ensure everything for pick-up is curbside by 7am on your collection day so Primrose can bring items to the designated collection location. Please label containers clearly, so the contractor can return them.

Safety

The contractors are required to conduct work in a safe manner, such as using traffic barrels and fencing off excavations. Please use extra caution in the construction zone to ensure everyone’s safety.