Bryne Drive North Extension

Project Type
Road Design
Project #
EN1278
Status
In Progress
Estimated Completion
2031

This roadway supports the new Harvie Road / Big Bay Point Road Highway 400 Crossing and will improve traffic flow across the south end of Barrie.

The Bryne Drive extension is split into a north segment (Harvie Road to Essa Road) and a south segment (Harvie Road to Caplan Avenue). The Bryne Drive South Extension opened in September 2024. 

Project Updates

September 23, 2024

Property acquisitions have pushed the expected completion of this design project to 2031.

Project Features

The Environmental Assessment and report were completed prior to detailed design commencement. The Stage 1 and Stage 2 Archaeological Assessment were completed as part of the greater Harvie Road/Highway 400 Crossing area improvements

  • Design for improved traffic flow parallel to Highway 400 with minimal environmental impacts
  • Construction of a new 5-lane roadway, complete with off-road bike lanes and sidewalks
  • Construction of a new sanitary sewer
  • Construction of a new watermain
  • New stormwater management ponds

Schedule

Construction of the Bryne Drive South Extension (Harvie Road to Caplan Avenue) was completed in September 2024.
Bryne Drive North Extension (Harvie Road to Essa Road)
Initial design2018–2024
Property acquisitions start2024
Potential design parameter changesTBD
Utility relocations startTBD
Construction start​TBD