Eastview Park Playground Revitalization & Site Works

Project Type
Parks & Forestry
Status
In Progress
Estimated Completion
Fall 2025

Eastview Community Park is located at 453 Grove Street East. The second phase of the park’s revitalization effort is underway. 

Phase 1

Phase 1 incorporated new dedicated acrylic pickleball courts, completed in October 2022. The construction includes a four-court battery with seating and a pathway. There was minimal impact on the tennis courts, playground, and community gardens. Access remained to all park assets, fields and amenities throughout construction.

Phase 2

Phase 2 focuses on:

  • Redesigning the playground area with all new play equipment
    Playground renderings are available below. View the play pod layout for details on the benefits of the various play structures. 
  • Resurfacing the tennis court 
  • Constructing a half court basketball facility
  • Providing lighting for the new pickleball courts
  • Providing a shade structure for gathering
  • Improving accessibility
  • Any additional site works that will improve usability of the space

Project Updates

September 16, 2025

Construction is progressing at a steady pace. Although some material delays have occurred, the project is anticipated be substantially completed before the end of October should no further delays occur. 

The central portion of the park remains closed to the public at this time. No unauthorized personnel are permitted within the fenced construction zone.

The soccer fields and arena, including the parking lot, remain open to the public; however, there remains no pedestrian throughway from Douglas Drive to the Eastview Arena until the project is completed.

Phase 2 Schedule

StageTiming
DesignJune 2023–January 2024
Anticipated ConstructionJune–Fall 2025
Phase 1 received funding.