Rose Street Watermain Replacement | Hwy 400 to Peel Street

Project Type
Road Construction
Project #
2024-137T
Status
Recently Completed

This project included watermain replacement on Rose Street, from the Highway 400 on-ramp to Peel Street. The project was awarded to Leading Edge Earthworks

This work was part of City Council's approved 2024 budget and aligns with a goal from Council’s strategic priorities to update and improve infrastructure throughout Barrie.

Project Updates

December 18, 2024

The Rose Street Watermain Replacement Project was successfully completed in mid-November. The watermain is fully integrated into Barrie's drinking water system. The completion of this work marks a significant milestone in enhancing our community’s water infrastructure and supporting the Bayfield Street/Highway 400 interchange design by the MTO. The project was delivered ahead of the initial estimated completion date in December.

Project Features

  • Disconnecting the existing cast iron watermain
  • Installing a new, larger watermain and new water services
  • Disconnecting the existing water services
  • Connecting new water services to the drinking water system
  • Restoring disturbed boulevards, curbs, and sidewalks
Image
map showing the work area | text: Key Plan
Map of the Work Area