Whiskey Creek Culvert & Channel Improvements | The Boulevard to Brennan Avenue

Project Type
Stormwater & Creeks
Project #
EN1486
Status
In Progress
Estimated Completion
2029

The lower section of Whiskey Creek, from The Boulevard to Lake Simcoe, has limited stormwater flow conveyance capacity and is prone to flooding. This project improves Whiskey Creek's conveyance capacity from The Boulevard to Brennan Avenue to reduce frequency of flooding. 

An environmental assessment study, completed in 2021, assessed solutions to mitigate flooding between The Boulevard and Kempenfelt Bay.

This project includes design and construction of the two culverts and watercourse improvements between the culverts to reduce the probability and consequence of flooding for both small frequent and large events. 

There will be minimal impacts to Minet's Point Park & Beach during construction.

Project Updates

November 19, 2025

The City has retained Salandria LTD. to demolish the structure located at 7 Brennan Avenue as part of the overall Whiskey Creek culvert & channel improvements project. The work is expected to begin before the end of the month and be completed in December.

During this work, drivers and nearby residents may experience construction-related noise, minor traffic delays, and other temporary inconveniences. A November 2025 info bulletin has been distributed to nearby properties. 

Schedule

StageTiming
Design2024–2026
Pre-Construction Works2026–2027
Anticipated Construction2028–2029