Performing Arts Centre

Project Type
Facilities
Status
In Progress
Estimated Completion
TBD

The vision for a theatre/performing arts centre within the downtown has been longstanding. The City’s 2006 Cultural Master Plan recommended the downtown as a logical, creative and natural home for the arts. 

Project Updates

January 19, 2026

  • The project has reached the 50% Design Development stage. Council has received the results of this phase and the Class C cost estimate for the Barrie Performing Arts Centre.
  • Staff are proceeding with the project as outlined in Staff Report FAC007-25 and detailed in the design documents prepared by Hariri Pontarini Architects (HPA).
  • A gala seating system will be included in the design, increasing the total project budget by $10M to $85M, as outlined in Staff Report FAC007-25.
  • Up to an additional 5,000 sq. ft. will be included in the design scope, funded incrementally at $1,000 per sq. ft. (up to $5M). Staff will report back to Executive Committee on the actual amount of space added and the associated cost.
  • HPA will be single-sourced to provide full professional services from the current design stage through to construction completion.

Design Considerations 

The proposed facility includes:

  • A 600-seat performance hall
  • A 200–25-seat rehearsal and events studio
  • All supporting amenities (lobby, backstage, production spaces)
  • A restaurant to activate the waterfront and generate additional revenue 
  • A gala seating system
  • Up to 5,000 square feet of additional program space to be incorporated into the design

Background 

As outlined in Staff Report ACC001-24, a report was prepared by Mr. Marshall Green to 
gather information and feedback from a range of stakeholder groups and organizations to 
help inform the vision for the waterfront and downtown area. On August 14, 2024, Mr. 
Green provided his report titled The Southshore, Barrie Sports, and a Revitalized 
Downtown. The report included a series of strategic recommendations related to the Barrie waterfront. Recommendation #6 specifically proposed that the former Sea Cadets site,  along with the necessary surrounding City-owned lands, be designated as the location for Barrie’s new Performing Arts Centre. Council subsequently provided the following staff direction under motion 24-G-223:

  1. Retain HPA be to complete a schematic design for a new Performing Arts Centre at the current Sea Cadets site at an estimated cost of $200,000, and that the design be prepared with the following considerations:
     
    • An approximately 45,000 sq. ft facility that includes both larger (600 seat) 
      and smaller (250 seat) performance spaces
       
    • The facility be designed with a maximum total building cost of $65M in hard 
      and soft construction costs for the building itself including fit out of all seating 
      and audio-visual components
  2. That staff undertake the required site due diligence (including but not limited to 
    geotechnical investigations) to determine the feasibility of utilizing the current 
    Sea Cadets site and any required surrounding City lands for a new Performing 
    Arts Centre, up to a maximum cost of $375,000 
  3. That staff report back to General Committee with the results of the due diligence 
    work and schematic design as well as the estimated required site works and a 
    potential implementation plan